Shri. Vijay Harischandra Kalgutkar vs Shri. Dayanand Harischandra Kalgutkar Advocate - G.V.NAIK — 3/2025
Case under Land Acquisition Act Section 30. Disposed: Contested--ALLOWED/GRANTED AFTER FULL HEARING on 13th March 2026.
L.A.C. - Land Acquisition Cases
CNR: KAUK020035342025
Filing Number
3/2025
Filing Date
02-12-2025
Registration No
3/2025
Registration Date
02-12-2025
Court
PRL. SENIOR CIVIL JUDGE AND CJM, KARWAR
Judge
594-ADDL. SNR. CIVIL JUDGE AND JMFC COURT, KARWAR
Decision Date
13th March 2026
Nature of Disposal
Contested--ALLOWED/GRANTED AFTER FULL HEARING
Acts & Sections
Petitioner(s)
Shri. Vijay Harischandra Kalgutkar
Adv. RENUKA PRASAD BHARADWAJ
Smt. Vasanti Harischandra Kalgutkar yaane Pooja Prakash Pednekar
Respondent(s)
Shri. Dayanand Harischandra Kalgutkar Advocate - G.V.NAIK
Special Land Acquisation Officer, Sea Bird Project, Karwar
Defence Estate Officer, Karnataka and Goa Circle,
Hearing History
Judge: 594-ADDL. SNR. CIVIL JUDGE AND JMFC COURT, KARWAR
Disposed
JUDGEMENT
ARGUMENTS
EVIDENCE
EVIDENCE
| Date | Purpose |
|---|---|
| 13-03-2026 | Disposed |
| 12-03-2026 | JUDGEMENT |
| 10-03-2026 | ARGUMENTS |
| 06-03-2026 | EVIDENCE |
| 05-03-2026 | EVIDENCE |
Final Orders / Judgements
Case Summary The Additional Senior Civil Judge at Karwar allowed the reference by the Special Land Acquisition Officer regarding apportionment of Rs. 43,57,155/- compensation for land acquired under the Sea Bird Project. The court determined that claimants Vijay Harischandra Kalgutkar and Vasanti Harischandra Kalgutkar, along with respondent Dayanand Harischandra Kalgutkar (the three children of the original landowner), are entitled to equal 1/3rd shares each in the compensation amount plus accrued interest from the fixed deposit held with State Bank of India, Karwar. This case analysis is maintained by casestatus.in based on publicly available court records.
Interim Orders
Case Summary The Additional Senior Civil Judge at Karwar allowed the reference by the Special Land Acquisition Officer regarding apportionment of Rs. 43,57,155/- compensation for land acquired under the Sea Bird Project. The court determined that claimants Vijay Harischandra Kalgutkar and Vasanti Harischandra Kalgutkar, along with respondent Dayanand Harischandra Kalgutkar (the three children of the original landowner), are entitled to equal 1/3rd shares each in the compensation amount plus accrued interest from the fixed deposit held with State Bank of India, Karwar. This case analysis is maintained by casestatus.in based on publicly available court records.