Dananjaya vs The Chief Manager, POWERGRID NM TRANSMISSION LIMITED Advocate - J Hudson Samuel and Partners — 101/2018
Case under U/s Section 19of,INDIAN,ELECTRICITY,ACT,U/Sec,16(3)OF,INDIAN,TELEGRAPHIC,.ACT. Status: ARGUMENTS.. Next hearing: 17th June 2026.
Misc - Miscellaneous Cases
CNR: KARN010021072018
Next Hearing
17th June 2026
Filing Number
101/2018
Filing Date
24-11-2018
Registration No
101/2018
Registration Date
24-11-2018
Court
PRL.DISTRICT AND SESSIONS JUDGE, RAMANAGARA
Judge
812-PRL. DISTRICT AND SESSIONS JUDGE
Acts & Sections
Petitioner(s)
Dananjaya
Adv. M.E. NIJALINGAPPA
Respondent(s)
The Chief Manager, POWERGRID NM TRANSMISSION LIMITED Advocate - J Hudson Samuel and Partners
The Deputy General Manager, M/s. Power Grid NM Transmission Limited
Adv. J Hudson Samuel and Partners
Hearing History
Judge: 812-PRL. DISTRICT AND SESSIONS JUDGE
ARGUMENTS.
ARGUMENTS.
ARGUMENTS.
EVIDENCE CIVIL
EVIDENCE CIVIL
| Date | Purpose |
|---|---|
| 22-04-2026 | ARGUMENTS. |
| 13-03-2026 | ARGUMENTS. |
| 13-02-2026 | ARGUMENTS. |
| 13-12-2025 | EVIDENCE CIVIL |
| 28-11-2025 | EVIDENCE CIVIL |
Interim Orders
Case Summary: Misc.101/18 - Dananjaya v. POWERGRID NM Transmission Limited This land acquisition dispute involves petitioner Dananjaya challenging compensation paid by POWERGRID for transmission line installation on his property (Survey No. 58/1). The case proceeded through witness examination across multiple hearings (January 2022 to November 2024). Dananjaya testified that POWERGRID laid a transmission line across 17 guntas of his land but compensated him for only 16 guntas, paying total compensation of ₹3,91,556 for unauthorized occupation, crop damage, and plant destruction. The case remains pending with cross-examination and no final judgment has been delivered. This case analysis is maintained by casestatus.in based on publicly available court records.
Case Summary: Misc.101/18 - Dananjaya v. POWERGRID NM Transmission Limited This land acquisition dispute involves petitioner Dananjaya challenging compensation paid by POWERGRID for transmission line installation on his property (Survey No. 58/1). The case proceeded through witness examination across multiple hearings (January 2022 to November 2024). Dananjaya testified that POWERGRID laid a transmission line across 17 guntas of his land but compensated him for only 16 guntas, paying total compensation of ₹3,91,556 for unauthorized occupation, crop damage, and plant destruction. The case remains pending with cross-examination and no final judgment has been delivered. This case analysis is maintained by casestatus.in based on publicly available court records.