MAHADEVA vs M/S ARATTUKULAM DEVELOPERS Advocate - Siddharth Suman — 17/2020

Case under Arbitration and Conciliation Act Section 34. Disposed: Contested--DISMISSED on 10th March 2026.

Com.A.P. - Commercial Arbitration Appeal

CNR: KABC170080552020

Case disposed

Filing Number

17/2020

Filing Date

19-02-2020

Registration No

17/2020

Registration Date

19-02-2020

Court

COMMERCIAL COURT,BENGALURU

Judge

1477-CCH-86 LXXXV ADDL. CITY CIVIL AND SESSIONS JUDGE

Decision Date

10th March 2026

Nature of Disposal

Contested--DISMISSED

Acts & Sections

Arbitration and Conciliation Act Section 34

Petitioner(s)

MAHADEVA

Adv. RAVINDRANATH B

KAVITHA

SHIRISH GOWDA

CHETHAN GOWDA

Respondent(s)

M/S ARATTUKULAM DEVELOPERS Advocate - Siddharth Suman

RAGHAVENDRA RAO G

Hearing History

Judge: 1477-CCH-86 LXXXV ADDL. CITY CIVIL AND SESSIONS JUDGE

10-03-2026

Disposed

06-03-2026

JUDGMENTS

28-02-2026

JUDGMENTS

18-02-2026

ORDERS

13-02-2026

ARGUMENTS

Final Orders / Judgements

10-03-2026
Judgment

Summary The Bengaluru Commercial Court dismissed a petition seeking to set aside an arbitral award in a Joint Development Agreement dispute. The court held that the arbitrator properly awarded Rs. 1,28,925/- monthly compensation for 45% project deficiency during July 2017 to May 2019, finding the developer liable for delays since the 15-month completion period should be calculated from plan sanction (February 2016), not the agreement date, and governmental delays do not excuse the developer's performance obligations. This case analysis is maintained by casestatus.in based on publicly available court records.

Interim Orders

04-04-2022
Judgment
casestatus.in Summary

Summary The Bengaluru Commercial Court dismissed a petition seeking to set aside an arbitral award in a Joint Development Agreement dispute. The court held that the arbitrator properly awarded Rs. 1,28,925/- monthly compensation for 45% project deficiency during July 2017 to May 2019, finding the developer liable for delays since the 15-month completion period should be calculated from plan sanction (February 2016), not the agreement date, and governmental delays do not excuse the developer's performance obligations. This case analysis is maintained by casestatus.in based on publicly available court records.

Browse Related Cases

More from this court

COMMERCIAL COURT,BENGALURU All courts →

Explore other courts

Search Another Case