VIJAYA SUBRAMANIYAN vs M/S GAURAV HOUSING DEVELOPMENT PVT LTD — 214/2025
Case under U/o 7 Rule 1 and 2 and R/w Sec 26 of Cpc. Disposed: Uncontested--DECREED on 09th March 2026.
Com.O.S. - Commercial Original Suit
CNR: KABC170006212025
Filing Number
212/2025
Filing Date
12-02-2025
Registration No
214/2025
Registration Date
12-02-2025
Court
COMMERCIAL COURT,BENGALURU
Judge
1477-CCH-86 LXXXV ADDL. CITY CIVIL AND SESSIONS JUDGE
Decision Date
09th March 2026
Nature of Disposal
Uncontested--DECREED
Acts & Sections
Petitioner(s)
VIJAYA SUBRAMANIYAN
Adv. Anirudh Suresh
RAJESWARI VENKATESH
K BALASUBRAMANIYAN
Respondent(s)
M/S GAURAV HOUSING DEVELOPMENT PVT LTD
SANCHIT GAURAV
Adv. ANUPAM AGARWAL
RAJIV RAMAN SINHA
Hearing History
Judge: 1477-CCH-86 LXXXV ADDL. CITY CIVIL AND SESSIONS JUDGE
Disposed
JUDGMENTS
JUDGMENTS
ARGUMENTS
ARGUMENTS
| Date | Purpose |
|---|---|
| 09-03-2026 | Disposed |
| 06-03-2026 | JUDGMENTS |
| 23-02-2026 | JUDGMENTS |
| 16-02-2026 | ARGUMENTS |
| 09-02-2026 | ARGUMENTS |
Final Orders / Judgements
Summary The Bangalore Commercial Court decreed the plaintiff's suit against Gaurav Housing Development Pvt Ltd and its directors, holding them jointly and severally liable to pay Rs. 55,00,000 with 12% interest (Rs. 66,55,000) to plaintiffs 1-2 from December 2014 to January 2025, and Rs. 35,00,000 with 12% interest (Rs. 48,65,000) to plaintiff 3 from June 2013 to January 2025, plus future interest at 12% p.a. until realization and litigation costs of Rs. 3,09,920. The dispute arose from a Joint Development Agreement dated April 2012 concerning residential properties in Bangalore. This case analysis is maintained by casestatus.in based on publicly available court records.
Interim Orders
Summary The Bangalore Commercial Court decreed the plaintiff's suit against Gaurav Housing Development Pvt Ltd and its directors, holding them jointly and severally liable to pay Rs. 55,00,000 with 12% interest (Rs. 66,55,000) to plaintiffs 1-2 from December 2014 to January 2025, and Rs. 35,00,000 with 12% interest (Rs. 48,65,000) to plaintiff 3 from June 2013 to January 2025, plus future interest at 12% p.a. until realization and litigation costs of Rs. 3,09,920. The dispute arose from a Joint Development Agreement dated April 2012 concerning residential properties in Bangalore. This case analysis is maintained by casestatus.in based on publicly available court records.