DYAVANNA SHETTY A C vs KANTHARAJ N R — 5848/2025
Case under U/s 166 Mv Act Section MVACT. Disposed: Uncontested--SETTLED BY ADR on 16th March 2026.
M.V.C. - ACCIDENT CLAIM CASES UNDER MOTOR VEHICLES ACT
CNR: KABC020311492025
Filing Number
5855/2025
Filing Date
12-Aug-2025
Registration No
5848/2025
Registration Date
12-Aug-2025
Court
CHIEF JUDGE, COURT OF SMALL CAUSES, BENGALURU
Judge
38-Scch - 13 - II Addl. Judge, Court of Small Causes and Acjm
Decision Date
16-Mar-2026
Nature of Disposal
Uncontested--SETTLED BY ADR
Last updated 10-Jun-2026
Acts & Sections
Petitioner(s)
-
1.DYAVANNA SHETTY A C
Adv. UMESHA R
Respondent(s)
-
1.KANTHARAJ N R
-
2.ICICI LOMB GEN INS CO LTD
Case History
-
Case disposedDisposed
-
16-Mar-2026
Orders
-
16-Mar-2026
Decree
The Motor Accident Claims Tribunal, Bangalore allowed petitioner Dyavanna Shetty A C's claim through settlement, awarding Rs. 2,00,000 (Two lakhs) in full and final compensation. Respondent no.2 (ICICI Lombard General Insurance Co Ltd) agreed to deposit the compensation amount before the court, with no costs awarded to the petitioner. This case analysis is maintained by casestatus.in based on publicly available court records.
-
16-Mar-2026
Disposed
Scch - 13 - II Addl. Judge, Court of Small Causes and Acjm
-
14-Mar-2026
Settlement
Scch - 13 - II Addl. Judge, Court of Small Causes and Acjm
-
28-Feb-2026
Settlement
Scch - 13 - II Addl. Judge, Court of Small Causes and Acjm
-
02-Feb-2026
Settlement
Scch - 13 - II Addl. Judge, Court of Small Causes and Acjm
-
13-Dec-2025
Settlement
Scch - 13 - II Addl. Judge, Court of Small Causes and Acjm
-
22-Nov-2025
Settlement
Scch - 13 - II Addl. Judge, Court of Small Causes and Acjm
-
23-Oct-2025
Summons
Scch - 13 - II Addl. Judge, Court of Small Causes and Acjm
-
23-Sep-2025
Summons
Scch - 13 - II Addl. Judge, Court of Small Causes and Acjm
-
13-Aug-2025
First hearing
Initial hearing scheduled
-
12-Aug-2025
Case filed
Registration No. 5848/2025
The Motor Accident Claims Tribunal, Bangalore allowed petitioner Dyavanna Shetty A C's claim through settlement, awarding Rs. 2,00,000 (Two lakhs) in full and final compensation. Respondent no.2 (ICICI Lombard General Insurance Co Ltd) agreed to deposit the compensation amount before the court, with no costs awarded to the petitioner. This case analysis is maintained by casestatus.in based on publicly available court records.