CHAMPABEN CHHAGANBHAI vs MORBI NAGAR PALIKA Advocate - G K BHATT — 49/2024
Case under Industrial Disputes Act, 1947 Section 33C. Disposed: Contested--JUDGEMENT on 01st April 2026.
RECO33C2 LC - Recovery 33C (2)
CNR: GJRJ180004952024
Filing Number
49/2024
Filing Date
02-03-2024
Registration No
49/2024
Registration Date
02-03-2024
Court
LABOUR COURT, RAJKOT
Judge
2-JUDGE, LABOUR COURT
Decision Date
01st April 2026
Nature of Disposal
Contested--JUDGEMENT
Acts & Sections
Petitioner(s)
CHAMPABEN CHHAGANBHAI
Adv. DHIRUBHAI MAKWANA
Respondent(s)
MORBI NAGAR PALIKA Advocate - G K BHATT
Hearing History
Judge: 2-JUDGE, LABOUR COURT
Disposed
For Order
For Arguement of opponent
For Arguement of opponent
For Evidence of opponent
| Date | Purpose |
|---|---|
| 01-04-2026 | Disposed |
| 11-03-2026 | For Order |
| 21-02-2026 | For Arguement of opponent |
| 16-02-2026 | For Arguement of opponent |
| 19-01-2026 | For Evidence of opponent |
Final Orders / Judgements
Summary The Morabi Labour Court allowed the worker's recovery application under the Industrial Disputes Act 1947, Section 33(2). The court ordered the municipal corporation to pay the worker ₹46,000 for unprovided uniforms (dress) from 1995-2018 and ₹4,000 for warm clothing, totaling ₹50,000 within 30 days, plus 12% interest for delayed payment. This case analysis is maintained by casestatus.in based on publicly available court records.
Summary The Morabi Labour Court allowed the worker's recovery application under the Industrial Disputes Act 1947, Section 33(2). The court ordered the municipal corporation to pay the worker ₹46,000 for unprovided uniforms (dress) from 1995-2018 and ₹4,000 for warm clothing, totaling ₹50,000 within 30 days, plus 12% interest for delayed payment. This case analysis is maintained by casestatus.in based on publicly available court records.