ALOK SUBHASH CHANDRA MISHRA vs HIMALAYA PAPTECH PVT. LTD. Advocate - P M VYAS — 8/2024
Case under Employees Compensation Act, 1923 Section 28. Disposed: Uncontested--ALLOWED on 09th March 2026.
AGRMNT LC - Aggrement
CNR: GJMH140000752024
Filing Number
8/2024
Filing Date
26-Apr-2024
Registration No
8/2024
Registration Date
26-Apr-2024
Court
LABOUR COURT, MAHESANA
Judge
1-Judge, Labour Court
Decision Date
09-Mar-2026
Nature of Disposal
Uncontested--ALLOWED
Last updated 13-Apr-2026
Acts & Sections
Petitioner(s)
-
1.ALOK SUBHASH CHANDRA MISHRA
Adv. PARUL GUPTA
Respondent(s)
-
1.HIMALAYA PAPTECH PVT. LTD. Advocate - P M VYAS
-
2.BAJAJ ALLIANZ GENERAL INSURANCE CO. LTD.
Case History
-
Case disposedDisposed
-
09-Mar-2026
JudegementView PDF
Summary The Labour Court at Mehsana approved and registered a workers' compensation settlement agreement whereby insurance company Bajaj Allianz deposited ₹3,25,261 as accident compensation for claimant Alok Subhashchandra Mishra. The court directed the deposit to be split: ₹30,261 plus accrued interest paid immediately to the claimant via cheque, and the remaining ₹2,95,000 placed in fixed deposit for one year in joint names of the claimant and commissioner, with accrued interest credited to the claimant's account. This case analysis is maintained by casestatus.in based on publicly available court records.
-
09-Mar-2026
Disposed
Judge, Labour Court
-
07-Mar-2026
For Order
Judge, Labour Court
-
31-Jan-2026
For Diposition of Applicant
Judge, Labour Court
-
03-Jan-2026
For Notice Serve to opponent
Judge, Labour Court
-
06-Dec-2025
For Notice Serve to opponent
Judge, Labour Court
-
01-Nov-2025
For Notice Serve to opponent
Judge, Labour Court
-
01-Oct-2025
For Notice Serve to opponent
Judge, Labour Court
-
01-Sep-2025
For Notice Serve to opponent
Judge, Labour Court
-
01-Aug-2025
For Notice Serve to opponent
Judge, Labour Court
-
11-Jul-2025
For Notice Serve to opponent
Judge, Labour Court
-
27-Jun-2025
For Notice Serve to opponent
Judge, Labour Court
-
30-May-2025
For Notice Serve to opponent
Judge, Labour Court
-
29-Apr-2025
For Notice Serve to opponent
Judge, Labour Court
-
29-Mar-2025
For Notice Serve to opponent
Judge, Labour Court
-
10-Mar-2025
For Notice Serve to opponent
Judge, Labour Court
-
01-Mar-2025
For Notice Serve to opponent
Judge, Labour Court
-
29-Jan-2025
For Notice Serve to opponent
Judge, Labour Court
-
01-Jan-2025
For Notice Serve to opponent
Judge, Labour Court
-
18-Dec-2024
For Notice Serve to opponent
Judge, Labour Court
-
13-Nov-2024
For Notice Serve to opponent
Judge, Labour Court (Jd)
-
18-Oct-2024
For Notice Serve to opponent
Judge, Labour Court (Jd)
-
05-Oct-2024
For Notice Serve to opponent
Judge, Labour Court (Jd)
-
16-Aug-2024
For Notice Serve to opponent
Judge, Labour Court (Jd)
-
05-Aug-2024
For Notice Serve to opponent
Judge, Labour Court (Jd)
-
10-Jul-2024
For Notice Serve to opponent
Judge, Labour Court (Jd)
-
26-Jun-2024
For Notice Serve to opponent
Judge, Labour Court (Jd)
-
19-Jun-2024
For Notice Serve to opponent
Judge, Labour Court (Jd)
-
05-Jun-2024
For Notice Serve to opponent
Judge, Labour Court (Jd)
-
24-May-2024
For Notice Serve to opponent
Judge, Labour Court (Jd)
-
20-May-2024
First hearing
Initial hearing scheduled
-
26-Apr-2024
Case filed
Registration No. 8/2024
Summary The Labour Court at Mehsana approved and registered a workers' compensation settlement agreement whereby insurance company Bajaj Allianz deposited ₹3,25,261 as accident compensation for claimant Alok Subhashchandra Mishra. The court directed the deposit to be split: ₹30,261 plus accrued interest paid immediately to the claimant via cheque, and the remaining ₹2,95,000 placed in fixed deposit for one year in joint names of the claimant and commissioner, with accrued interest credited to the claimant's account. This case analysis is maintained by casestatus.in based on publicly available court records.