RABARI BABABHAI LILABHAI vs Government of Gujarat Advocate - APP — 39/2017

Case under Land Acquisition Act, 1894 Section 18. Disposed: Contested--PARTLY ALLOWED on 18th March 2026.

LAR - LAND ACQUISITION REFERENCE CASE

CNR: GJMH050007802017

Case disposed

e-Filing Number

-

Filing Number

39/2017

Filing Date

05-03-2007

Registration No

39/2017

Registration Date

05-03-2007

Court

TALUKA COURT, KHERALU

Judge

2-PRINCIPAL SENIOR CIVIL JUDGE & ADDL. CJM

Decision Date

18th March 2026

Nature of Disposal

Contested--PARTLY ALLOWED

Acts & Sections

LAND ACQUISITION ACT, 1894 Section 18

Petitioner(s)

RABARI BABABHAI LILABHAI

Adv. J H PATEL

Respondent(s)

Government of Gujarat Advocate - APP (Assistant Public Prosecutor)

Hearing History

Judge: 2-PRINCIPAL SENIOR CIVIL JUDGE & ADDL. CJM

18-03-2026

Disposed

16-03-2026

JUDGEMENT

16-03-2026

JUDGEMENT

16-03-2026

JUDGEMENT

16-03-2026

JUDGEMENT

Final Orders / Judgements

18-03-2026
JUDEGEMENT

Summary This is a consolidated Land Acquisition Reference judgment from a Principal Senior Civil Judge in Kheralu, Gujarat (dated 18/03/2026) regarding multiple Land Acquisition Reference Cases (Nos. 32/2017 to 39/2017) for the Sabarmati Saraswati Link Canal project in Mandali village, Kheralu taluka, Mehsana district. The court's key decision: The court partially allowed the claimants' references and awarded them additional compensation of Rs. 192.98 per square meter over the original award of Rs. 10 per square meter. The court also granted 30% solatium, 12% annual appreciation from notification date to award date, and interest at 9% for the first year and 15% thereafter on the enhanced compensation amount. The court rejected claims for losses from land fragmentation, trees, and business losses as unsubstantiated. This case analysis is maintained by casestatus.in based on publicly available court records.

casestatus.in Summary

Summary This is a consolidated Land Acquisition Reference judgment from a Principal Senior Civil Judge in Kheralu, Gujarat (dated 18/03/2026) regarding multiple Land Acquisition Reference Cases (Nos. 32/2017 to 39/2017) for the Sabarmati Saraswati Link Canal project in Mandali village, Kheralu taluka, Mehsana district. The court's key decision: The court partially allowed the claimants' references and awarded them additional compensation of Rs. 192.98 per square meter over the original award of Rs. 10 per square meter. The court also granted 30% solatium, 12% annual appreciation from notification date to award date, and interest at 9% for the first year and 15% thereafter on the enhanced compensation amount. The court rejected claims for losses from land fragmentation, trees, and business losses as unsubstantiated. This case analysis is maintained by casestatus.in based on publicly available court records.

Browse Related Cases

Cases under same legislation

More from this court

TALUKA COURT, KHERALU All courts →

Explore other courts

Search Another Case