CHAUDHRY JITABEN VELABHAI vs Government of Gujarat Advocate - APP — 35/2017

Case under Land Acquisition Act, 1894 Section 018,. Disposed: Contested--PARTLY ALLOWED on 18th March 2026.

LAR - LAND ACQUISITION REFERENCE CASE

CNR: GJMH050007762017

Case disposed

e-Filing Number

-

Filing Number

35/2017

Filing Date

05-03-2007

Registration No

35/2017

Registration Date

05-03-2007

Court

TALUKA COURT, KHERALU

Judge

2-PRINCIPAL SENIOR CIVIL JUDGE & ADDL. CJM

Decision Date

18th March 2026

Nature of Disposal

Contested--PARTLY ALLOWED

Acts & Sections

LAND ACQUISITION ACT, 1894 Section 018,

Petitioner(s)

CHAUDHRY JITABEN VELABHAI

Adv. J H PATEL

Respondent(s)

Government of Gujarat Advocate - APP (Assistant Public Prosecutor)

MARG MAKAN VIBHAG

Adv. C S RAJPUT

Hearing History

Judge: 2-PRINCIPAL SENIOR CIVIL JUDGE & ADDL. CJM

18-03-2026

Disposed

16-03-2026

JUDGEMENT

16-03-2026

JUDGEMENT

16-03-2026

JUDGEMENT

16-03-2026

JUDGEMENT

Final Orders / Judgements

18-03-2026
JUDEGEMENT

Summary The court partially allowed the Land Acquisition Reference (LAR) case, determining that landowners whose agricultural land in Mandali village, Kheralu taluka was permanently acquired for the Sabarmati-Saraswati Link Canal project are entitled to additional compensation of Rs. 172.98 per square meter (beyond the originally awarded Rs. 10 per sq. meter). The court also awarded 12% annual appreciation from the notification date until the award date, plus 30% solatium and interest at 9% for the first year and 15% thereafter on all additional amounts due. This case analysis is maintained by casestatus.in based on publicly available court records.

casestatus.in Summary

Summary The court partially allowed the Land Acquisition Reference (LAR) case, determining that landowners whose agricultural land in Mandali village, Kheralu taluka was permanently acquired for the Sabarmati-Saraswati Link Canal project are entitled to additional compensation of Rs. 172.98 per square meter (beyond the originally awarded Rs. 10 per sq. meter). The court also awarded 12% annual appreciation from the notification date until the award date, plus 30% solatium and interest at 9% for the first year and 15% thereafter on all additional amounts due. This case analysis is maintained by casestatus.in based on publicly available court records.