PGVCL - THROUGH DY. ENGINEER - RAMBAUG SUB DIVISION vs KAMLESH SHIVABHAI CHAUHAN — 525/2025
Case under Code of Civil Procedure Section 34. Disposed: Uncontested--EX-PARTE JUDGEMENT on 06th May 2026.
RCS - REGULAR CIVIL SUIT
CNR: GJKT110048762025
Filing Number
525/2025
Filing Date
09-Jun-2025
Registration No
525/2025
Registration Date
09-Jun-2025
Court
TALUKA COURT, GANDHIDHAM
Judge
33-4th Addl. Sr. CIVIL Judge & A.C.J.M.
Decision Date
06-May-2026
Nature of Disposal
Uncontested--EX-PARTE JUDGEMENT
Last updated 21-May-2026
Acts & Sections
Petitioner(s)
-
1.PGVCL - THROUGH DY. ENGINEER - RAMBAUG SUB DIVISION
Adv. H N ASNANI
Respondent(s)
-
1.KAMLESH SHIVABHAI CHAUHAN
Case History
-
Case disposedDisposed
-
06-May-2026
JudegementView PDF
The court partially allowed PGVCL's suit for electricity bill recovery against the defendant. The court found that the defendant had illegally consumed Rs.14,068.56 worth of electricity by bypassing the meter, and ordered him to pay this principal amount with 6% per annum interest from the date of suit filing. However, the court rejected the claimed delay payment charges of Rs.5,681.96 and reduced the requested 15% interest to 6% per annum, as the plaintiff failed to justify the higher rate. This case analysis is maintained by casestatus.in based on publicly available court records.
-
06-May-2026
Disposed
4th Addl. Sr. CIVIL Judge & A.C.J.M.
-
05-May-2026
Judgement
4th Addl. Sr. CIVIL Judge & A.C.J.M.
-
28-Apr-2026
Judgement
4th Addl. Sr. CIVIL Judge & A.C.J.M.
-
22-Apr-2026
Judgement
4th Addl. Sr. CIVIL Judge & A.C.J.M.
-
09-Apr-2026
Plaintiff Evidence
4th Addl. Sr. CIVIL Judge & A.C.J.M.
-
08-Apr-2026
Issues
4th Addl. Sr. CIVIL Judge & A.C.J.M.
-
11-Mar-2026
Public Notice
4th Addl. Sr. CIVIL Judge & A.C.J.M.
-
11-Feb-2026
Public Notice
4th Addl. Sr. CIVIL Judge & A.C.J.M.
-
28-Jan-2026
Public Notice
4th Addl. Sr. CIVIL Judge & A.C.J.M.
-
02-Jan-2026
Summons - Notice
4th Addl. Sr. CIVIL Judge & A.C.J.M.
-
08-Dec-2025
Summons - Notice
3rd Addl. Sr. CIVIL Judge & A.C.J.M.
-
19-Nov-2025
Summons - Notice
3rd Addl. Sr. CIVIL Judge & A.C.J.M.
-
09-Oct-2025
Summons - Notice
3rd Addl. Sr. CIVIL Judge & A.C.J.M.
-
19-Sep-2025
Summons - Notice
3rd Addl. Sr. CIVIL Judge & A.C.J.M.
-
29-Aug-2025
Summons - Notice
3rd Addl. Sr. CIVIL Judge & A.C.J.M.
-
13-Aug-2025
Summons - Notice
3rd Addl. Sr. CIVIL Judge & A.C.J.M.
-
14-Jul-2025
First hearing
Initial hearing scheduled
-
09-Jun-2025
Case filed
Registration No. 525/2025
The court partially allowed PGVCL's suit for electricity bill recovery against the defendant. The court found that the defendant had illegally consumed Rs.14,068.56 worth of electricity by bypassing the meter, and ordered him to pay this principal amount with 6% per annum interest from the date of suit filing. However, the court rejected the claimed delay payment charges of Rs.5,681.96 and reduced the requested 15% interest to 6% per annum, as the plaintiff failed to justify the higher rate. This case analysis is maintained by casestatus.in based on publicly available court records.
Explore other courts