PGVCL GANDHIDHAM SUB DIVISION-THROUGH DEPUTY ENGINEER vs MAHESHVARI DAMYANTIBEN SHANKARLAL URFE SHANKARBHAI — 459/2025

Case under Code of Civil Procedure Section 34. Disposed: Uncontested--EX-PARTE JUDGEMENT on 08th May 2026.

RCS - REGULAR CIVIL SUIT

CNR: GJKT110039822025

Case disposed

Filing Number

459/2025

Filing Date

01-05-2025

Registration No

459/2025

Registration Date

01-05-2025

Court

TALUKA COURT, GANDHIDHAM

Judge

32-ADDI CIVIL JUDGE & J.M.F.C

Decision Date

08th May 2026

Nature of Disposal

Uncontested--EX-PARTE JUDGEMENT

Acts & Sections

CODE OF CIVIL PROCEDURE, 1908 Section 34

Petitioner(s)

PGVCL GANDHIDHAM SUB DIVISION-THROUGH DEPUTY ENGINEER

Adv. H N ASNANI

Respondent(s)

MAHESHVARI DAMYANTIBEN SHANKARLAL URFE SHANKARBHAI

Hearing History

Judge: 32-ADDI CIVIL JUDGE & J.M.F.C

08-05-2026

Disposed

01-05-2026

JUDGEMENT

02-04-2026

JUDGEMENT

11-03-2026

PLAINTIFF EVIDENCE

06-03-2026

PLAINTIFF EVIDENCE

Final Orders / Judgements

08-05-2026
JUDEGEMENT

Summary The Additional Civil Judge at Gandhidham partially allowed Paschim Gujarat Vij Company Ltd.'s suit against the defendant for recovery of electricity theft arrears. The court found that the defendant illegally tampered with the service line and committed electricity theft, resulting in dues of Rs.35,457/-. The court awarded the full amount with interest at 6% per annum (instead of the claimed 15%) from the date of filing until realization, plus litigation costs against the defendant. This case analysis is maintained by casestatus.in based on publicly available court records.

casestatus.in Summary

Summary The Additional Civil Judge at Gandhidham partially allowed Paschim Gujarat Vij Company Ltd.'s suit against the defendant for recovery of electricity theft arrears. The court found that the defendant illegally tampered with the service line and committed electricity theft, resulting in dues of Rs.35,457/-. The court awarded the full amount with interest at 6% per annum (instead of the claimed 15%) from the date of filing until realization, plus litigation costs against the defendant. This case analysis is maintained by casestatus.in based on publicly available court records.

Browse Related Cases

Cases under same legislation

More from this court

TALUKA COURT, GANDHIDHAM All courts →

Explore other courts

Search Another Case