PGVCL RAMBAUG SUB DIVISION -THROUGH DEPUTY ENGINEER vs JANGIYA MAMAD BACHU — 225/2025

Case under Code of Civil Procedure Section 34. Disposed: Uncontested--EX-PARTE JUDGEMENT on 06th May 2026.

Case disposed

RCS - REGULAR CIVIL SUIT

CNR: GJKT110018092025

Filing Number

225/2025

Filing Date

25-Feb-2025

Registration No

225/2025

Registration Date

25-Feb-2025

Court

TALUKA COURT, GANDHIDHAM

Judge

33-4th Addl. Sr. CIVIL Judge & A.C.J.M.

Decision Date

06-May-2026

Nature of Disposal

Uncontested--EX-PARTE JUDGEMENT

Last updated 21-May-2026

Acts & Sections

Code of Civil Procedure Section 34

Petitioner(s)

  1. 1.PGVCL RAMBAUG SUB DIVISION -THROUGH DEPUTY ENGINEER

    Adv. G V PARYANI

Respondent(s)

  1. 1.JANGIYA MAMAD BACHU

Case History

  1. Case disposedDisposed

  2. 06-May-2026

    JudegementView PDF

    Court Decision Summary The 4th Additional Senior Civil Judge at Gandhidham partially allowed PGVCL's suit for recovery of unpaid electricity charges against the defendant. The court ordered the defendant to pay Rs. 11,287.57 (principal electricity dues) with 6% per annum interest from the suit filing date, plus Rs. 1,528.42 as delay payment charges, rejecting the plaintiff's claim for 15% interest due to lack of documentary evidence supporting that rate. This case analysis is maintained by casestatus.in based on publicly available court records.

  3. 06-May-2026

    Disposed

    4th Addl. Sr. CIVIL Judge & A.C.J.M.

  4. 29-Apr-2026

    Judgement

    4th Addl. Sr. CIVIL Judge & A.C.J.M.

  5. 22-Apr-2026

    Judgement

    4th Addl. Sr. CIVIL Judge & A.C.J.M.

  6. 16-Apr-2026

    Plaintiffs Evidence

    4th Addl. Sr. CIVIL Judge & A.C.J.M.

  7. 15-Apr-2026

    Issues

    4th Addl. Sr. CIVIL Judge & A.C.J.M.

  8. 11-Mar-2026

    Public Notice

    4th Addl. Sr. CIVIL Judge & A.C.J.M.

  9. 04-Feb-2026

    Public Notice

    4th Addl. Sr. CIVIL Judge & A.C.J.M.

  10. 21-Nov-2025

    Public Notice

    3rd Addl. Sr. CIVIL Judge & A.C.J.M.

  11. 28-Oct-2025

    Public Notice

    3rd Addl. Sr. CIVIL Judge & A.C.J.M.

  12. 18-Oct-2025

    Public Notice

    3rd Addl. Sr. CIVIL Judge & A.C.J.M.

  13. 13-Oct-2025

    Public Notice

    3rd Addl. Sr. CIVIL Judge & A.C.J.M.

  14. 03-Sep-2025

    Public Notice

    3rd Addl. Sr. CIVIL Judge & A.C.J.M.

  15. 24-Jul-2025

    Public Notice

    3rd Addl. Sr. CIVIL Judge & A.C.J.M.

  16. 05-Jul-2025

    Summons - Notice

    3rd Addl. Sr. CIVIL Judge & A.C.J.M.

  17. 25-Jun-2025

    Summons - Notice

    3rd Addl. Sr. CIVIL Judge & A.C.J.M.

  18. 26-May-2025

    Public Notice

    Addi CIVIL Judge & J.M.F.C

  19. 05-May-2025

    Public Notice

    Addi CIVIL Judge & J.M.F.C

  20. 23-Apr-2025

    Public Notice

    Addi CIVIL Judge & J.M.F.C

  21. 16-Apr-2025

    Public Notice

    Addi CIVIL Judge & J.M.F.C

  22. 09-Apr-2025

    Summons - Notice

    Addi CIVIL Judge & J.M.F.C

  23. 21-Mar-2025

    Summons - Notice

    Addi CIVIL Judge & J.M.F.C

  24. 06-Mar-2025

    First hearing

    Initial hearing scheduled

  25. 25-Feb-2025

    Case filed

    Registration No. 225/2025

casestatus.in Summary

Court Decision Summary The 4th Additional Senior Civil Judge at Gandhidham partially allowed PGVCL's suit for recovery of unpaid electricity charges against the defendant. The court ordered the defendant to pay Rs. 11,287.57 (principal electricity dues) with 6% per annum interest from the suit filing date, plus Rs. 1,528.42 as delay payment charges, rejecting the plaintiff's claim for 15% interest due to lack of documentary evidence supporting that rate. This case analysis is maintained by casestatus.in based on publicly available court records.