PGVCL GANDHIDHAM SUB DIVISION -THROUGH DEPUTY ENGINEER vs LALJI KARSAN — 194/2025
Case under Code of Civil Procedure Section 34. Disposed: Uncontested--EX-PARTE JUDGEMENT on 29th April 2026.
RCS - REGULAR CIVIL SUIT
CNR: GJKT110017662025
Filing Number
194/2025
Filing Date
24-02-2025
Registration No
194/2025
Registration Date
24-02-2025
Court
TALUKA COURT, GANDHIDHAM
Judge
33-4th ADDL. SR. CIVIL JUDGE & A.C.J.M.
Decision Date
29th April 2026
Nature of Disposal
Uncontested--EX-PARTE JUDGEMENT
Acts & Sections
Petitioner(s)
PGVCL GANDHIDHAM SUB DIVISION -THROUGH DEPUTY ENGINEER
Adv. H N ASNANI
Respondent(s)
LALJI KARSAN
Hearing History
Judge: 33-4th ADDL. SR. CIVIL JUDGE & A.C.J.M.
Disposed
JUDGEMENT
JUDGEMENT
PLAINTIFF EVIDENCE
ISSUES
| Date | Purpose |
|---|---|
| 29-04-2026 | Disposed |
| 27-04-2026 | JUDGEMENT |
| 22-04-2026 | JUDGEMENT |
| 09-04-2026 | PLAINTIFF EVIDENCE |
| 08-04-2026 | ISSUES |
Final Orders / Judgements
The court partially allowed PGVCL's suit for recovery of unpaid electricity bills against defendant Lalji Karshan, directing him to pay Rs. 10,554.49 (principal) with 6% annual interest from the suit's institution date, plus Rs. 2,243.64 in delay payment charges. The court rejected the claimed 15% interest as unjustified, finding 6% reasonable in the absence of a contractual agreement. This case analysis is maintained by casestatus.in based on publicly available court records.
The court partially allowed PGVCL's suit for recovery of unpaid electricity bills against defendant Lalji Karshan, directing him to pay Rs. 10,554.49 (principal) with 6% annual interest from the suit's institution date, plus Rs. 2,243.64 in delay payment charges. The court rejected the claimed 15% interest as unjustified, finding 6% reasonable in the absence of a contractual agreement. This case analysis is maintained by casestatus.in based on publicly available court records.