PGVCL LTD THROUGH DY, ENGINEER - RAMBAUG SUB DIVISION ADIPUR vs BRAHMAN NARESH MULARAM — 133/2025
Case under Code of Civil Procedure Section 34. Disposed: Uncontested--EX-PARTE JUDGEMENT on 06th May 2026.
RCS - REGULAR CIVIL SUIT
CNR: GJKT110015912025
Filing Number
133/2025
Filing Date
19-02-2025
Registration No
133/2025
Registration Date
19-02-2025
Court
TALUKA COURT, GANDHIDHAM
Judge
33-4th ADDL. SR. CIVIL JUDGE & A.C.J.M.
Decision Date
06th May 2026
Nature of Disposal
Uncontested--EX-PARTE JUDGEMENT
Acts & Sections
Petitioner(s)
PGVCL LTD THROUGH DY, ENGINEER - RAMBAUG SUB DIVISION ADIPUR
Adv. H N ASNANI
Respondent(s)
BRAHMAN NARESH MULARAM
Hearing History
Judge: 33-4th ADDL. SR. CIVIL JUDGE & A.C.J.M.
Disposed
JUDGEMENT
JUDGEMENT
JUDGEMENT
PLAINTIFF EVIDENCE
| Date | Purpose |
|---|---|
| 06-05-2026 | Disposed |
| 29-04-2026 | JUDGEMENT |
| 27-04-2026 | JUDGEMENT |
| 22-04-2026 | JUDGEMENT |
| 09-04-2026 | PLAINTIFF EVIDENCE |
Final Orders / Judgements
Summary The court partially allowed PGVCL's suit for electricity bill recovery against the defendant. The court found the defendant liable to pay the principal amount of Rs. 51,085.70 with 6% per annum interest (reducing the claimed 15%), but rejected the delay payment charges of Rs. 17,504.40 due to insufficient justification by the plaintiff. This case analysis is maintained by casestatus.in based on publicly available court records.
Summary The court partially allowed PGVCL's suit for electricity bill recovery against the defendant. The court found the defendant liable to pay the principal amount of Rs. 51,085.70 with 6% per annum interest (reducing the claimed 15%), but rejected the delay payment charges of Rs. 17,504.40 due to insufficient justification by the plaintiff. This case analysis is maintained by casestatus.in based on publicly available court records.