PRAVINBHAI BHIKHUBHAI SAGAR vs VIPULBHAI DHIRUBHAI GAJERA — 238/2025
Case under Code of Civil Procedure Section 9. Disposed: Contested--PARTLY ALLOWED on 06th May 2026.
RCS - REGULAR CIVIL SUIT
CNR: GJJN020092042025
Filing Number
238/2025
Filing Date
03-12-2025
Registration No
238/2025
Registration Date
03-12-2025
Court
CIVIL COURT JUNAGADH
Judge
2-PRINCIPAL SENIOR CIVIL JUDGE & ADDL. CJM
Decision Date
06th May 2026
Nature of Disposal
Contested--PARTLY ALLOWED
Acts & Sections
Petitioner(s)
PRAVINBHAI BHIKHUBHAI SAGAR
Adv. K D ODEDRA
Respondent(s)
VIPULBHAI DHIRUBHAI GAJERA
Hearing History
Judge: 2-PRINCIPAL SENIOR CIVIL JUDGE & ADDL. CJM
Disposed
JUDGEMENT
JUDGEMENT
FINAL ARGUMENTS
DEFENDANT EVIDENCE
| Date | Purpose |
|---|---|
| 06-05-2026 | Disposed |
| 29-04-2026 | JUDGEMENT |
| 07-04-2026 | JUDGEMENT |
| 24-03-2026 | FINAL ARGUMENTS |
| 13-03-2026 | DEFENDANT EVIDENCE |
Final Orders / Judgements
Summary of Case 238/2025 Court: Primary Senior Civil Court, Junagadh Parties: Pravinbhai Bhikhubhai Sagar (Petitioner) v. Vipulbhai Dhirubhai Gajera (Respondent) Decision: The court partially allowed the petitioner's claim. The court decreed that the respondent must execute and register a complete sale deed for the disputed property (a plot in Joshipur, Junagadh, with constructed building blocks) within one month. Alternatively, if the respondent fails to do so, the petitioner may obtain the registered deed through a court-appointed commissioner. The court found the petitioner had paid the full purchase price (Rs. 17,00,000) and fulfilled all contractual obligations, while the respondent unjustifiably delayed executing the final deed despite receiving payment and delivering possession. This case analysis is maintained by casestatus.in based on publicly available court records.
Summary of Case 238/2025 Court: Primary Senior Civil Court, Junagadh Parties: Pravinbhai Bhikhubhai Sagar (Petitioner) v. Vipulbhai Dhirubhai Gajera (Respondent) Decision: The court partially allowed the petitioner's claim. The court decreed that the respondent must execute and register a complete sale deed for the disputed property (a plot in Joshipur, Junagadh, with constructed building blocks) within one month. Alternatively, if the respondent fails to do so, the petitioner may obtain the registered deed through a court-appointed commissioner. The court found the petitioner had paid the full purchase price (Rs. 17,00,000) and fulfilled all contractual obligations, while the respondent unjustifiably delayed executing the final deed despite receiving payment and delivering possession. This case analysis is maintained by casestatus.in based on publicly available court records.
Browse Related Cases
Cases under same legislation
Explore other courts