PGVCL THROUGH DEPUTY ENGINEER vs SALIMBHAI RAHIMBHAI SHEKH — 137/2025

Case under Code of Civil Procedure Section 37. Disposed: Contested--DECREE SATISFIED on 17th April 2026.

Case disposed

EXE R - EXECUTION PETITION - REGULAR

CNR: GJJN020081132025

Filing Number

137/2025

Filing Date

04-Oct-2025

Registration No

137/2025

Registration Date

04-Oct-2025

Court

CIVIL COURT JUNAGADH

Judge

7-2nd Addl. Sr. CIVIL Judge & A.C.J.M.

Decision Date

17-Apr-2026

Nature of Disposal

Contested--DECREE SATISFIED

Last updated 07-Jun-2026

Acts & Sections

Code of Civil Procedure Section 37

Petitioner(s)

  1. 1.PGVCL THROUGH DEPUTY ENGINEER

    Adv. N A SHETH

Respondent(s)

  1. 1.SALIMBHAI RAHIMBHAI SHEKH

Case History

  1. Case disposedDisposed

  2. 17-Apr-2026

    Order

    The court ordered the respondent Salimbhai Rahimbhai Shekh to pay the outstanding electricity dues claimed by PGVCL (petitioner) as per the demand notice, with the condition that failure to pay would result in no further action on the case. The judgment was delivered on 17th April 2026 by the Junagadh Civil Court. This case analysis is maintained by casestatus.in based on publicly available court records.

  3. 17-Apr-2026

    Disposed

    2nd Addl. Sr. CIVIL Judge & A.C.J.M.

  4. 03-Apr-2026

    Warrant Of Attachment

    2nd Addl. Sr. CIVIL Judge & A.C.J.M.

  5. 14-Mar-2026

    Warrant Of Attachment

    2nd Addl. Sr. CIVIL Judge & A.C.J.M.

  6. 13-Mar-2026

    Warrant Of Attachment

    2nd Addl. Sr. CIVIL Judge & A.C.J.M.

  7. 07-Mar-2026

    Warrant Of Attachment

    2nd Addl. Sr. CIVIL Judge & A.C.J.M.

  8. 26-Feb-2026

    Warrant Of Attachment

    2nd Addl. Sr. CIVIL Judge & A.C.J.M.

  9. 12-Feb-2026

    Process Of Execution

    2nd Addl. Sr. CIVIL Judge & A.C.J.M.

  10. 19-Jan-2026

    Process Of Execution

    2nd Addl. Sr. CIVIL Judge & A.C.J.M.

  11. 05-Jan-2026

    Process Of Execution

    2nd Addl. Sr. CIVIL Judge & A.C.J.M.

  12. 19-Dec-2025

    Process Of Execution

    2nd Addl. Sr. CIVIL Judge & A.C.J.M.

  13. 21-Nov-2025

    Process Of Execution

    2nd Addl. Sr. CIVIL Judge & A.C.J.M.

  14. 01-Nov-2025

    Process Of Execution

    2nd Addl. Sr. CIVIL Judge & A.C.J.M.

  15. 04-Oct-2025

    First hearing

    Initial hearing scheduled

  16. 04-Oct-2025

    Case filed

    Registration No. 137/2025

casestatus.in Summary

The court ordered the respondent Salimbhai Rahimbhai Shekh to pay the outstanding electricity dues claimed by PGVCL (petitioner) as per the demand notice, with the condition that failure to pay would result in no further action on the case. The judgment was delivered on 17th April 2026 by the Junagadh Civil Court. This case analysis is maintained by casestatus.in based on publicly available court records.