PGVCL THROUGH DTY ENGINEER vs KHETABHAI BHIKHABHAI BHUNDIYA — 106/2025

Case under Code of Civil Procedure Section 9. Disposed: Uncontested--EX on 16th March 2026.

Case disposed

RCS - REGULAR CIVIL SUIT

CNR: GJJM110017432025

Filing Number

106/2025

Filing Date

06-Sep-2025

Registration No

106/2025

Registration Date

06-Sep-2025

Court

TALUKA COURT, KALAVAD

Judge

1-Principal CIVIL Judge & J.M.F.C

Decision Date

16-Mar-2026

Nature of Disposal

Uncontested--EX

Last updated 12-Jun-2026

Acts & Sections

Code of Civil Procedure Section 9

Petitioner(s)

  1. 1.PGVCL THROUGH DTY ENGINEER

    Adv. P D JADEJA

Respondent(s)

  1. 1.KHETABHAI BHIKHABHAI BHUNDIYA

Case History

  1. Case disposedDisposed

  2. 16-Mar-2026

    JudegementView PDF

    Case Summary: 106/2025 Court Decision: The court partially allowed PGVCL's claim against Khetabhai Bhikhabhai Bhundiya, ordering the defendant to pay Rs. 26,450.85 (the electricity theft recovery amount) plus 6% annual interest from the claim date, along with costs. The court found the defendant liable for unlawful electricity theft based on the power company's inspection report and documentary evidence, despite the defendant's failure to contest the claim. This case analysis is maintained by casestatus.in based on publicly available court records.

  3. 16-Mar-2026

    Disposed

    Principal CIVIL Judge & J.M.F.C

  4. 10-Feb-2026

    Final Arguments

    Principal CIVIL Judge & J.M.F.C

  5. 20-Jan-2026

    Plaintiff Evidence

    Principal CIVIL Judge & J.M.F.C

  6. 22-Dec-2025

    Plaintiff Evidence

    Principal CIVIL Judge & J.M.F.C

  7. 15-Nov-2025

    Plaintiff Evidence

    Principal CIVIL Judge & J.M.F.C

  8. 13-Oct-2025

    Written Statement/Reply

    Principal CIVIL Judge & J.M.F.C

  9. 06-Sep-2025

    First hearing

    Initial hearing scheduled

  10. 06-Sep-2025

    Case filed

    Registration No. 106/2025

casestatus.in Summary

Case Summary: 106/2025 Court Decision: The court partially allowed PGVCL's claim against Khetabhai Bhikhabhai Bhundiya, ordering the defendant to pay Rs. 26,450.85 (the electricity theft recovery amount) plus 6% annual interest from the claim date, along with costs. The court found the defendant liable for unlawful electricity theft based on the power company's inspection report and documentary evidence, despite the defendant's failure to contest the claim. This case analysis is maintained by casestatus.in based on publicly available court records.

Explore other courts