P.G.V.C.L BOTAD RURAL vs HARESHBHAI DIYALBHAI MAKHNA Advocate - EX PARTY — 4/2026
Case under Code of Civil Procedure Section 9. Disposed: Uncontested--EX-PARTE JUDGEMENT on 25th March 2026.
RCS - REGULAR CIVIL SUIT
CNR: GJBT020000362026
Filing Number
4/2026
Filing Date
01-Jan-2026
Registration No
4/2026
Registration Date
01-Jan-2026
Court
CIVIL COURT, BOTAD
Judge
3-Principal Senior CIVIL Judge
Decision Date
25-Mar-2026
Nature of Disposal
Uncontested--EX-PARTE JUDGEMENT
Last updated 11-Jun-2026
Acts & Sections
Petitioner(s)
-
1.P.G.V.C.L BOTAD RURAL
Adv. V G VADODARIA
Respondent(s)
-
1.HARESHBHAI DIYALBHAI MAKHNA Advocate - EX PARTY
Case History
-
Case disposedDisposed
-
25-Mar-2026
JudegementView PDF
Case Summary: 4/2026 Court Decision: The court partly allowed PGVCL's suit, ordering defendant Hareshbhai Diyalbhai Makhna to pay Rs. 34,343.19 (principal amount for illegal electricity consumption) plus 6% simple interest per annum from filing date. The court rejected the claimed 24% interest rate as unsupported by contract or statute, deeming 6% fair and reasonable under commercial trends. Key Reasoning: Operating ex-parte, the court found uncontroverted evidence—through witness affidavit, inspection reports, and documentary evidence—establishing that defendant illegally tapped 261 watts from PGVCL's power line without authorization. The defendant's non-appearance and failure to challenge the evidence left the plaintiff's case unchallenged, satisfying the prima facie burden required in ex-parte proceedings. This case analysis is maintained by casestatus.in based on publicly available court records.
-
25-Mar-2026
Disposed
Principal Senior CIVIL Judge
-
16-Mar-2026
Final Arguments
Principal Senior CIVIL Judge
-
02-Mar-2026
Plaintiff Evidence
Principal Senior CIVIL Judge
-
17-Feb-2026
Issues
Principal Senior CIVIL Judge
-
02-Feb-2026
Summons - Notice
Principal Senior CIVIL Judge
-
01-Jan-2026
First hearing
Initial hearing scheduled
-
01-Jan-2026
Case filed
Registration No. 4/2026
Case Summary: 4/2026 Court Decision: The court partly allowed PGVCL's suit, ordering defendant Hareshbhai Diyalbhai Makhna to pay Rs. 34,343.19 (principal amount for illegal electricity consumption) plus 6% simple interest per annum from filing date. The court rejected the claimed 24% interest rate as unsupported by contract or statute, deeming 6% fair and reasonable under commercial trends. Key Reasoning: Operating ex-parte, the court found uncontroverted evidence—through witness affidavit, inspection reports, and documentary evidence—establishing that defendant illegally tapped 261 watts from PGVCL's power line without authorization. The defendant's non-appearance and failure to challenge the evidence left the plaintiff's case unchallenged, satisfying the prima facie burden required in ex-parte proceedings. This case analysis is maintained by casestatus.in based on publicly available court records.