DEPUTY ENGINEER SHRI P.G.V.C.L VALLABHIPUR SUB DIVISION vs RAMESHBHAI JADAVBHAI BHADBHIDIYA — 64/2025
Case under Electricity Act, 2003 Section 45. Disposed: Uncontested--EX-PARTE JUDGEMENT on 30th March 2026.
RCS - REGULAR CIVIL SUIT
CNR: GJBN120009112025
Filing Number
64/2025
Filing Date
08-10-2025
Registration No
64/2025
Registration Date
08-10-2025
Court
TALUKA COURT, VALLABHIPUR
Judge
1-PRINCIPAL CIVIL JUDGE & J.M.F.C
Decision Date
30th March 2026
Nature of Disposal
Uncontested--EX-PARTE JUDGEMENT
Acts & Sections
Petitioner(s)
DEPUTY ENGINEER SHRI P.G.V.C.L VALLABHIPUR SUB DIVISION
Adv. M R JOSHI
Respondent(s)
RAMESHBHAI JADAVBHAI BHADBHIDIYA
Hearing History
Judge: 1-PRINCIPAL CIVIL JUDGE & J.M.F.C
Disposed
JUDGEMENT
FINAL ARGUMENTS
PLAINTIFF EVIDENCE
For Written Statement
| Date | Purpose |
|---|---|
| 30-03-2026 | Disposed |
| 13-03-2026 | JUDGEMENT |
| 27-02-2026 | FINAL ARGUMENTS |
| 09-02-2026 | PLAINTIFF EVIDENCE |
| 05-01-2026 | For Written Statement |
Final Orders / Judgements
The court partially allowed the petitioner's suit for recovery of electricity dues. The Deputy Engineer of Western Gujarat Electricity Company sought to recover ₹8,813.87 from the respondent for unauthorized electricity theft (642 HP) detected during inspection on 09/10/2023. The court found the respondent liable and ordered payment of the full claimed amount with 6% annual interest from the date of the suit until recovery, reducing the requested 18% interest. The respondent failed to appear or contest the allegations, resulting in ex-parte proceedings decided in the petitioner's favor. This case analysis is maintained by casestatus.in based on publicly available court records.
The court partially allowed the petitioner's suit for recovery of electricity dues. The Deputy Engineer of Western Gujarat Electricity Company sought to recover ₹8,813.87 from the respondent for unauthorized electricity theft (642 HP) detected during inspection on 09/10/2023. The court found the respondent liable and ordered payment of the full claimed amount with 6% annual interest from the date of the suit until recovery, reducing the requested 18% interest. The respondent failed to appear or contest the allegations, resulting in ex-parte proceedings decided in the petitioner's favor. This case analysis is maintained by casestatus.in based on publicly available court records.