DEPUTY ENGINEER SHRI P.G.V.C.L VALLABHIPUR SUB DIVISION vs PAMUBEN DILIPBHAI VEGAD — 57/2025

Case under Electricity Act, 2003 Section 45. Disposed: Uncontested--EX-PARTE JUDGEMENT on 30th March 2026.

Case disposed

RCS - REGULAR CIVIL SUIT

CNR: GJBN120009042025

Filing Number

57/2025

Filing Date

08-Oct-2025

Registration No

57/2025

Registration Date

08-Oct-2025

Court

TALUKA COURT, VALLABHIPUR

Judge

1-Principal CIVIL Judge & J.M.F.C

Decision Date

30-Mar-2026

Nature of Disposal

Uncontested--EX-PARTE JUDGEMENT

Last updated 31-May-2026

Acts & Sections

Electricity Act, 2003 Section 45

Petitioner(s)

  1. 1.DEPUTY ENGINEER SHRI P.G.V.C.L VALLABHIPUR SUB DIVISION

    Adv. M R JOSHI

Respondent(s)

  1. 1.PAMUBEN DILIPBHAI VEGAD

Case History

  1. Case disposedDisposed

  2. 30-Mar-2026

    JudegementView PDF

    Case Summary: RCS 57/2025 Court Decision: The Principal Civil Judge, Vallabhipur, partially granted the electricity company's claim against the consumer. The court ordered the respondent to pay ₹2,19,275.17 (principal amount) plus simple interest at 6% per annum from the date of filing until recovery, rejecting the petitioner's request for 18% interest. The respondent must also bear court costs. Key Facts: The petitioner (West Gujarat Electricity Company) disconnected the respondent's electricity connection on 31 October 2025 for non-payment of bills and minimum charges totaling ₹2,19,275.17. Despite legal notices, the respondent failed to respond or appear in court, resulting in an ex-parte judgment in the petitioner's favor based on documentary and oral evidence presented. This case analysis is maintained by casestatus.in based on publicly available court records.

  3. 30-Mar-2026

    Disposed

    Principal CIVIL Judge & J.M.F.C

  4. 13-Mar-2026

    Judgement

    Principal CIVIL Judge & J.M.F.C

  5. 27-Feb-2026

    Final Arguments

    Principal CIVIL Judge & J.M.F.C

  6. 09-Feb-2026

    Plaintiff Evidence

    Principal CIVIL Judge & J.M.F.C

  7. 05-Jan-2026

    For Written Statement

    Principal CIVIL Judge & J.M.F.C

  8. 22-Dec-2025

    For Written Statement

    Principal CIVIL Judge & J.M.F.C

  9. 08-Dec-2025

    For Written Statement

    Principal CIVIL Judge & J.M.F.C

  10. 24-Nov-2025

    For Written Statement

    Principal CIVIL Judge & J.M.F.C

  11. 04-Nov-2025

    Summons - Notice

    Principal CIVIL Judge & J.M.F.C

  12. 03-Nov-2025

    Summons - Notice

    Principal CIVIL Judge & J.M.F.C

  13. 08-Oct-2025

    First hearing

    Initial hearing scheduled

  14. 08-Oct-2025

    Case filed

    Registration No. 57/2025

casestatus.in Summary

Case Summary: RCS 57/2025 Court Decision: The Principal Civil Judge, Vallabhipur, partially granted the electricity company's claim against the consumer. The court ordered the respondent to pay ₹2,19,275.17 (principal amount) plus simple interest at 6% per annum from the date of filing until recovery, rejecting the petitioner's request for 18% interest. The respondent must also bear court costs. Key Facts: The petitioner (West Gujarat Electricity Company) disconnected the respondent's electricity connection on 31 October 2025 for non-payment of bills and minimum charges totaling ₹2,19,275.17. Despite legal notices, the respondent failed to respond or appear in court, resulting in an ex-parte judgment in the petitioner's favor based on documentary and oral evidence presented. This case analysis is maintained by casestatus.in based on publicly available court records.