PGVCL Gariyadhar Through Its Deputy Engineer vs GOVINDBHAI JASMATBHAI GOHIL — 255/2025

Case under Electricity Act, 2003 Section 54. Disposed: Uncontested--EX-PARTE JUDGEMENT on 23rd April 2026.

Case disposed

RCS - REGULAR CIVIL SUIT

CNR: GJBN060010422025

Filing Number

255/2025

Filing Date

07-Oct-2025

Registration No

255/2025

Registration Date

07-Oct-2025

Court

TALUKA COURT, GARIADHAR

Judge

1-Principal CIVIL Judge & J.M.F.C

Decision Date

23-Apr-2026

Nature of Disposal

Uncontested--EX-PARTE JUDGEMENT

Last updated 31-May-2026

Acts & Sections

Electricity Act, 2003 Section 54

Petitioner(s)

  1. 1.PGVCL Gariyadhar Through Its Deputy Engineer

    Adv. I L PARMAR

Respondent(s)

  1. 1.GOVINDBHAI JASMATBHAI GOHIL

Case History

  1. Case disposedDisposed

  2. 23-Apr-2026

    Judegement

    Summary of RCS No. 255 of 2025 The court partially granted PGVCL's claim against respondent Govindbhai Jasmatbhai Gohil for unpaid electricity dues of ₹14,954.38. The court ordered the respondent to pay the outstanding amount plus 6% annual interest from the date of filing until recovery, along with case costs, while holding the respondent's property liable for collection. This case analysis is maintained by casestatus.in based on publicly available court records.

  3. 23-Apr-2026

    Disposed

    Principal CIVIL Judge & J.M.F.C

  4. 13-Mar-2026

    Judgement

    Principal CIVIL Judge & J.M.F.C

  5. 30-Jan-2026

    Plaintiff Evidence

    Principal CIVIL Judge & J.M.F.C

  6. 19-Dec-2025

    Plaintiff Evidence

    Principal CIVIL Judge & J.M.F.C

  7. 27-Nov-2025

    Plaintiff Evidence

    Principal CIVIL Judge & J.M.F.C

  8. 12-Nov-2025

    Written Statement

    Principal CIVIL Judge & J.M.F.C

  9. 07-Oct-2025

    First hearing

    Initial hearing scheduled

  10. 07-Oct-2025

    Case filed

    Registration No. 255/2025

casestatus.in Summary

Summary of RCS No. 255 of 2025 The court partially granted PGVCL's claim against respondent Govindbhai Jasmatbhai Gohil for unpaid electricity dues of ₹14,954.38. The court ordered the respondent to pay the outstanding amount plus 6% annual interest from the date of filing until recovery, along with case costs, while holding the respondent's property liable for collection. This case analysis is maintained by casestatus.in based on publicly available court records.

Explore other courts