PGVCL Gariyadhar Through Its Deputy Engineer vs MAHESHBHAI RUPABHAI KANTARIYA — 31/2026
Case under Electricity Act, 2003 Section 54. Disposed: Uncontested--EX-PARTE JUDGEMENT on 07th May 2026.
RCS - REGULAR CIVIL SUIT
CNR: GJBN060000692026
Filing Number
31/2026
Filing Date
29-Jan-2026
Registration No
31/2026
Registration Date
29-Jan-2026
Court
TALUKA COURT, GARIADHAR
Judge
1-Principal CIVIL Judge & J.M.F.C
Decision Date
07-May-2026
Nature of Disposal
Uncontested--EX-PARTE JUDGEMENT
Last updated 31-May-2026
Acts & Sections
Petitioner(s)
-
1.PGVCL Gariyadhar Through Its Deputy Engineer
Adv. I L PARMAR
Respondent(s)
-
1.MAHESHBHAI RUPABHAI KANTARIYA
Case History
-
Case disposedDisposed
-
07-May-2026
Judegement
Summary of Case 31/2026 The court partially allowed PGVCL's claim against respondent Maheshbhai Rupabhai Kantariya for unauthorized electricity consumption. The court awarded Rs. 20,297.81 plus 6% annual interest from the date of filing until recovery, finding that the respondent had illegally tapped into the power supply line without authorization. The court rejected the petitioner's claim for 18% interest and instead applied the statutory rate of 6% under the Civil Procedure Code. This case analysis is maintained by casestatus.in based on publicly available court records.
-
07-May-2026
Disposed
Principal CIVIL Judge & J.M.F.C
-
02-May-2026
Judgement
Principal CIVIL Judge & J.M.F.C
-
29-Apr-2026
Plaintiff Evidence
Principal CIVIL Judge & J.M.F.C
-
13-Mar-2026
Defendant Evidence
Principal CIVIL Judge & J.M.F.C
-
29-Jan-2026
First hearing
Initial hearing scheduled
-
29-Jan-2026
Case filed
Registration No. 31/2026
Summary of Case 31/2026 The court partially allowed PGVCL's claim against respondent Maheshbhai Rupabhai Kantariya for unauthorized electricity consumption. The court awarded Rs. 20,297.81 plus 6% annual interest from the date of filing until recovery, finding that the respondent had illegally tapped into the power supply line without authorization. The court rejected the petitioner's claim for 18% interest and instead applied the statutory rate of 6% under the Civil Procedure Code. This case analysis is maintained by casestatus.in based on publicly available court records.