PGVCL Gariyadhar Through Its Deputy Engineer vs KHODABHAI GANDABHAI KANTARIYA — 19/2025
Case under Electricity Act, 2003 Section 54. Disposed: Uncontested--EX-PARTE JUDGEMENT on 23rd April 2026.
RCS - REGULAR CIVIL SUIT
CNR: GJBN060000232025
Filing Number
19/2025
Filing Date
02-Jan-2025
Registration No
19/2025
Registration Date
02-Jan-2025
Court
TALUKA COURT, GARIADHAR
Judge
1-Principal CIVIL Judge & J.M.F.C
Decision Date
23-Apr-2026
Nature of Disposal
Uncontested--EX-PARTE JUDGEMENT
Last updated 31-May-2026
Acts & Sections
Petitioner(s)
-
1.PGVCL Gariyadhar Through Its Deputy Engineer
Adv. I L PARMAR
Respondent(s)
-
1.KHODABHAI GANDABHAI KANTARIYA
Case History
-
Case disposedDisposed
-
23-Apr-2026
Judegement
Case Summary: RCS No. 19/2025 Court Decision: The court partially allowed PGVCL's claim against the respondent for unauthorized electricity usage. The court found the respondent guilty of theft of electrical power by illegally connecting to the power supply line without authorization and ordered recovery of Rs. 29,170/61 (including minimum charges and surcharges) with 6% annual interest from the date of claim until payment, enforceable against the respondent's property. This case analysis is maintained by casestatus.in based on publicly available court records.
-
23-Apr-2026
Disposed
Principal CIVIL Judge & J.M.F.C
-
13-Mar-2026
Judgement
Principal CIVIL Judge & J.M.F.C
-
30-Jan-2026
Plaintiff Evidence
Principal CIVIL Judge & J.M.F.C
-
19-Dec-2025
Plaintiff Evidence
Principal CIVIL Judge & J.M.F.C
-
27-Nov-2025
Plaintiff Evidence
Principal CIVIL Judge & J.M.F.C
-
04-Nov-2025
Plaintiff Evidence
Principal CIVIL Judge & J.M.F.C
-
25-Sep-2025
Plaintiff Evidence
Principal CIVIL Judge & J.M.F.C
-
12-Aug-2025
Plaintiff Evidence
Principal CIVIL Judge & J.M.F.C
-
18-Jul-2025
Plaintiff Evidence
Principal CIVIL Judge & J.M.F.C
-
18-Jun-2025
Plaintiff Evidence
Principal CIVIL Judge & J.M.F.C
-
07-May-2025
Plaintiff Evidence
Principal CIVIL Judge & J.M.F.C
-
24-Apr-2025
Summons - Notice
Principal CIVIL Judge & J.M.F.C
-
08-Apr-2025
Summons - Notice
Principal CIVIL Judge & J.M.F.C
-
05-Mar-2025
Summons - Notice
Principal CIVIL Judge & J.M.F.C
-
02-Jan-2025
First hearing
Initial hearing scheduled
-
02-Jan-2025
Case filed
Registration No. 19/2025
Case Summary: RCS No. 19/2025 Court Decision: The court partially allowed PGVCL's claim against the respondent for unauthorized electricity usage. The court found the respondent guilty of theft of electrical power by illegally connecting to the power supply line without authorization and ordered recovery of Rs. 29,170/61 (including minimum charges and surcharges) with 6% annual interest from the date of claim until payment, enforceable against the respondent's property. This case analysis is maintained by casestatus.in based on publicly available court records.
Explore other courts