THE DEPUTY GENERAL MANAGER PROJECT IMPLEMENTATION UNIT N.H. 52 vs RAMJANAM SHARMA @ RAMJANAM SINGH AND OTHER — 112/2024
Case under Arbitration Act Section 34. Status: addmission. Next hearing: 11th September 2026.
Civil Miscellaneous
CNR: BRGA010142722024
Filing Number
824/2024
Filing Date
05-Sep-2024
Registration No
112/2024
Registration Date
05-Sep-2024
Court
Gaya DJ Div.
Judge
1-Principal District and Sessions Judge
Last updated 17-Aug-2026
Acts & Sections
Petitioner(s)
-
1.THE DEPUTY GENERAL MANAGER PROJECT IMPLEMENTATION UNIT N.H. 52
Adv. RABINDRA PRASAD
Respondent(s)
-
1.RAMJANAM SHARMA @ RAMJANAM SINGH AND OTHER
-
2.STATE OF BIHAR THROUGH THE COLLECTOR
-
3.THE COMPETENT AUTHORITY CUM THE DISTRICT LAND ACQUISITION OFFICER
Case History
-
11-Sep-2026
Next hearingPending
-
03-Aug-2026
addmission
Principal District and Sessions Judge
-
03-Jul-2026
addmission
Principal District and Sessions Judge
-
26-May-2026
addmission
Principal District and Sessions Judge
-
10-Apr-2026
addmission
Principal District and Sessions Judge
-
21-Feb-2026
addmission
Principal District and Sessions Judge
-
17-Dec-2025
addmission
Principal District and Sessions Judge
-
31-Oct-2025
addmission
Principal District and Sessions Judge
-
09-Sep-2025
addmission
Principal District and Sessions Judge
-
02-Aug-2025
addmission
Principal District and Sessions Judge
-
01-Jul-2025
addmission
Principal District and Sessions Judge
-
20-May-2025
addmission
Principal District and Sessions Judge
-
28-Mar-2025
addmission
Principal District and Sessions Judge
-
05-Feb-2025
addmission
Principal District and Sessions Judge
-
02-Jan-2025
addmission
Principal District and Sessions Judge
-
26-Nov-2024
addmission
Principal District and Sessions Judge
-
19-Oct-2024
addmission
Principal District and Sessions Judge
-
20-Sep-2024
addmission
Principal District and Sessions Judge
-
07-Sep-2024
First hearing
Initial hearing scheduled
-
05-Sep-2024
Case filed
Registration No. 112/2024