SUDHA DEVI AND OTHER vs THE PROJECT DIRECTOR PROJECT IMPLEMENTATION UNIT NO 2 AND OTHER — 71/2025
Case under Highways Act(bihar & Orissa) Section 3H(4). Status: Hearing. Next hearing: 10th June 2026.
Civil Miscellaneous
CNR: BRGA010091012025
Filing Number
431/2025
Filing Date
31-May-2025
Registration No
71/2025
Registration Date
31-May-2025
Court
Gaya DJ Div.
Judge
1-Principal District and Sessions Judge
Last updated 07-May-2026
Acts & Sections
Petitioner(s)
-
1.SUDHA DEVI AND OTHER
Adv. UDAY KUMAR
Respondent(s)
-
1.THE PROJECT DIRECTOR PROJECT IMPLEMENTATION UNIT NO 2 AND OTHER
-
2.THE STATE OF BIHAR THROUGH THE COLLECTOR
-
3.THE DISTRICT LAND ACQUISITION OFFICER CUM COMPETENT AUTHORITY NH2
Case History
-
10-Jun-2026
Next hearingPending
-
30-Apr-2026
Hearing
Principal District and Sessions Judge
-
20-Apr-2026
Restored
Principal District and Sessions Judge
-
20-Apr-2026
Hearing
Principal District and Sessions Judge
-
17-Mar-2026
Disposed
Principal District and Sessions Judge
-
10-Mar-2026
Stistedar Report
Principal District and Sessions Judge
-
02-Mar-2026
Stistedar Report
Principal District and Sessions Judge
-
30-Jan-2026
Stistedar Report
Principal District and Sessions Judge
-
20-Dec-2025
Stistedar Report
Principal District and Sessions Judge
-
20-Nov-2025
Stistedar Report
Principal District and Sessions Judge
-
30-Oct-2025
addmission
Principal District and Sessions Judge
-
24-Sep-2025
addmission
Principal District and Sessions Judge
-
23-Aug-2025
addmission
Principal District and Sessions Judge
-
08-Aug-2025
addmission
Principal District and Sessions Judge
-
08-Jul-2025
addmission
Principal District and Sessions Judge
-
23-Jun-2025
addmission
Principal District and Sessions Judge
-
03-Jun-2025
First hearing
Initial hearing scheduled
-
31-May-2025
Case filed
Registration No. 71/2025