M/s Reinforced Earth Pvt Ltd REIPL vs Ms Amar Infrastructure Ltd Advocate - AVINASH CHAND SAHU, ,PRIYA SHARMA,AMAN TAMRAKAR,AMIT NAYAK — ARBR/38/2025

Status: Orders on IAs. Next hearing: : -.

Orders on IAs Next hearing —

CNR: CGHC010336402025

e-Filing Number

31-07-2025

Filing Number

ARBR/20998/2025

Filing Date

31-Jul-2025

Registration No

ARBR/38/2025

Registration Date

02-Aug-2025

Judge

Hon'ble The Chief Justice

Coram

Hon'ble The Chief Justice

Bench Type

Single Bench

Category

ARBITRATION MATTERS ( 11 )

Sub-Category

PETITIONS FOR APPOINTMENT OF ARBITRATOR UNDER THE SCHEME FRAMED BY ( 1101 )

Judicial Branch

Civil Section

Last updated 27-Mar-2026

Petitioner(s)

  1. 1.M/s Reinforced Earth Pvt Ltd REIPL

    Adv. Navin Shukla,HARSHITA DUBEY,HARSHITA DUBEY, ,SHAMSUDDIN MIRZA,SMITA JHA,Ali Afzaal Mirza,SURAJ JAISWAL,SURAJ JAISWAL,AHMED AYAAN MIRZA,AHMED AYAAN MIRZA

Respondent(s)

  1. 1.Ms Amar Infrastructure Ltd Advocate - AVINASH CHAND SAHU, ,PRIYA SHARMA,AMAN TAMRAKAR,AMIT NAYAK

Case History

  1. Next hearingPending

  2. 23-Mar-2026

    Hon'ble The Chief JusticeView PDF

    Case Status Summary: In ARBR No. 38 of 2025 before the High Court of Chhattisgarh, the case between M/s Reinforced Earth Pvt Ltd (REIPL) and Ms Amar Infrastructure Ltd was adjourned for two weeks. The respondent's counsel requested additional time to comply with the court's order dated 05.01.2026, which was granted by Chief Justice Ramesh Sinha. This case analysis is maintained by casestatus.in based on publicly available court records.

  3. 05-Jan-2026

    Hon'ble The Chief JusticeView PDF

  4. 17-Nov-2025

    Hon'ble The Chief JusticeView PDF

  5. 13-Oct-2025

    Hon'ble The Chief JusticeView PDF

  6. 06-Aug-2025

    Hon'ble The Chief JusticeView PDF

  7. 06-Aug-2025

    Fresh Matters

    Hon'ble The Chief Justice

  8. 31-Jul-2025

    Case filed

    Registration No. ARBR/38/2025

casestatus.in Summary

Case Status Summary: In ARBR No. 38 of 2025 before the High Court of Chhattisgarh, the case between M/s Reinforced Earth Pvt Ltd (REIPL) and Ms Amar Infrastructure Ltd was adjourned for two weeks. The respondent's counsel requested additional time to comply with the court's order dated 05.01.2026, which was granted by Chief Justice Ramesh Sinha. This case analysis is maintained by casestatus.in based on publicly available court records.

Explore other courts