NAYAN KUMARI vs STATE OF CHHATTISGARH Advocate - A.G. — WPC/1430/2026

Disposed: Uncontested--DISPOSED OFF on 15th April 2026.

Case disposed

CNR: CGHC010122732026

Filing Number

WPC/7060/2026

Filing Date

24-Mar-2026

Registration No

WPC/1430/2026

Registration Date

27-Mar-2026

Judge

Hon'ble Shri Justice Naresh Kumar Chandravanshi

Coram

Hon'ble Shri Justice Naresh Kumar Chandravanshi

Bench Type

Single Bench

Category

LAND ACQUISITION & REQUISITION MATTERS ( 5 )

Sub-Category

OTHERS AND MIXED BAG ONES. ( 504 )

Judicial Branch

Writ Section

Decision Date

15-Apr-2026

Nature of Disposal

Uncontested--DISPOSED OFF

Last updated 22-May-2026

Petitioner(s)

  1. 1.NAYAN KUMARI

    Adv. Pranjal Agrawal,RAMAKANT PATEL,RAMAKANT PATEL, ,RAMAKANT PATEL

Respondent(s)

  1. 1.STATE OF CHHATTISGARH Advocate - A.G.

  2. 2.Secretary

  3. 3.Collector

  4. 4.Sub Divisional Officer (R) Cum Land Acquisition Officer

  5. 5.Executive Engineer

Case History

  1. Case disposedDisposed

  2. 15-Apr-2026

    Hon'ble Shri Justice Naresh Kumar ChandravanshiView PDF

    The High Court of Chhattisgarh disposed of a petition by directing the respondent authorities to verify the petitioner's claim that her agricultural land (Khasra No. 814/4, 0.13 acre) in village Chandrapur came under the submergence area of Kalma Bairaj dam and initiate land acquisition proceedings accordingly. The court granted the petitioner 15 days to file a fresh representation, and directed authorities to complete verification, initiate acquisition proceedings if necessary, and determine compensation within 90 days. This case analysis is maintained by casestatus.in based on publicly available court records.

  3. 30-Mar-2026

    For Orders [On Office Notes]

    Additional Registrar(j)

  4. 24-Mar-2026

    Case filed

    Registration No. WPC/1430/2026

casestatus.in Summary

The High Court of Chhattisgarh disposed of a petition by directing the respondent authorities to verify the petitioner's claim that her agricultural land (Khasra No. 814/4, 0.13 acre) in village Chandrapur came under the submergence area of Kalma Bairaj dam and initiate land acquisition proceedings accordingly. The court granted the petitioner 15 days to file a fresh representation, and directed authorities to complete verification, initiate acquisition proceedings if necessary, and determine compensation within 90 days. This case analysis is maintained by casestatus.in based on publicly available court records.

Explore other courts

Search Another Case