ANAND SURANA vs THE OFFICE OF THE ELECTRICITY OMBUDSMAN — WPC/1270/2026

Next hearing: : -.

Next hearing —

CNR: CGHC010105812026

Filing Number

WPC/6053/2026

Filing Date

12-Mar-2026

Registration No

WPC/1270/2026

Registration Date

19-Mar-2026

Judge

Hon'ble Shri Justice Naresh Kumar Chandravanshi

Coram

Hon'ble Shri Justice Naresh Kumar Chandravanshi

Bench Type

Single Bench

Category

ORDINARY CIVIL MATTERS ( 17 )

Sub-Category

MATTERS RELATING TO ELECTRICITY DISPUTES (CONNECTION / DISCONNECTION ETC.). ( 1710 )

Judicial Branch

Writ Section

Last updated 16-Apr-2026

Petitioner(s)

  1. 1.ANAND SURANA

    Adv. ADHIRAJ SURANA,shobhit koshta,shobhit koshta, ,PRAVESH SAHU,P R PATANKAR,shobhit koshta

Respondent(s)

  1. 1.THE OFFICE OF THE ELECTRICITY OMBUDSMAN

  2. 2.Rajendra Surana

  3. 3.Office of Executive Engineer (O and M)

    Adv. MAYANK CHANDRAKAR

  4. 4.Office of Chief Engineer

Case History

  1. Next hearingPending

  2. 25-Mar-2026

    Hon'ble Shri Justice Naresh Kumar ChandravanshiView PDF

    Summary: The High Court of Chhattisgarh (WPC No. 1270 of 2026) granted interim relief to the petitioner whose electricity connection was disconnected following an Electricity Ombudsman order dated 20.01.2026. The court directed respondents 3 and 4 (State Power Distribution Company officials) to reconnect the petitioner's electricity supply within 2 days as an interim measure. Notice was issued to respondents 1 and 2, and the case is listed for hearing in the week commencing 27.04.2026. This case analysis is maintained by casestatus.in based on publicly available court records.

  3. 20-Mar-2026

    For Orders [On Office Notes]

    Additional Registrar(j)

  4. 12-Mar-2026

    Case filed

    Registration No. WPC/1270/2026

casestatus.in Summary

Summary: The High Court of Chhattisgarh (WPC No. 1270 of 2026) granted interim relief to the petitioner whose electricity connection was disconnected following an Electricity Ombudsman order dated 20.01.2026. The court directed respondents 3 and 4 (State Power Distribution Company officials) to reconnect the petitioner's electricity supply within 2 days as an interim measure. Notice was issued to respondents 1 and 2, and the case is listed for hearing in the week commencing 27.04.2026. This case analysis is maintained by casestatus.in based on publicly available court records.

Explore other courts

Search Another Case