R.K. TRANSPORT AND CONSTRUCTION LIMITED vs AMBIKA PROJECT — FA/62/2025
Next hearing: : -.
CNR: CGHC010088052025
Filing Number
FA/4934/2025
Filing Date
28-Feb-2025
Registration No
FA/62/2025
Registration Date
19-Mar-2025
Judge
Hon'ble Shri Justice Sanjay K. Agrawal , Hon'ble Shri Justice Sachin Singh Rajput
Coram
Hon'ble Shri Justice Sanjay K. Agrawal , Hon'ble Shri Justice Sachin Singh Rajput
Bench Type
Division Bench
Category
ORDINARY CIVIL MATTERS ( 17 )
Sub-Category
OTHERS AND MIXED BAG ONES.. ( 1750 )
Judicial Branch
Civil Section
Last updated 22-May-2026
Petitioner(s)
-
1.R.K. TRANSPORT AND CONSTRUCTION LIMITED
Adv. Rishabh Garg,Akash Kumar Kundu,Akash Kumar Kundu, ,KSHITIJ SHARMA,Pragalbha Sharma,RUCHI NAGAR,PAYAL JAIN,Akash Kumar Kundu
Respondent(s)
-
1.AMBIKA PROJECT
Case History
-
—
Next hearingPending
-
15-Apr-2026
Hon'ble Shri Justice Sanjay K. Agrawal,Hon'ble Shri Justice Sachin Singh RajputView PDF
Summary: In FA No. 62 of 2025 before the High Court of Chhattisgarh at Bilaspur (R.K. Transport and Construction Limited vs. Ambika Project), the court allowed the condonation of delay applications (I.A. No. 01 and I.A. No. 02) and admitted the appeal on 11.09.2025. The court issued notice to the respondent, directed payment of process fee and copies within 7 days, and granted six weeks for filing the paper book. In the latest order dated 15.04.2026, two weeks' time was granted to the appellant's counsel to cure default(s) pointed out by the Registry. This case analysis is maintained by casestatus.in based on publicly available court records.
-
11-Sep-2025
Hon'ble Shri Justice Sanjay K. Agrawal,Hon'ble Shri Justice Radhakishan AgrawalView PDF
-
08-Sep-2025
Orders on IAs ( Dormant Case )
Hon'ble Smt. Justice Rajani Dubey , Hon'ble Shri Justice Amitendra Kishore Prasad
-
10-Jun-2025
Hon'ble Smt. Justice Rajani Dubey,Hon'ble Shri Justice Amitendra Kishore PrasadView PDF
-
21-Mar-2025
Hon'ble Shri Justice Sanjay K. Agrawal,Hon'ble Shri Justice Sanjay Kumar JaiswalView PDF
-
21-Mar-2025
First hearing
Initial hearing scheduled
-
28-Feb-2025
Case filed
Registration No. FA/62/2025
Summary: In FA No. 62 of 2025 before the High Court of Chhattisgarh at Bilaspur (R.K. Transport and Construction Limited vs. Ambika Project), the court allowed the condonation of delay applications (I.A. No. 01 and I.A. No. 02) and admitted the appeal on 11.09.2025. The court issued notice to the respondent, directed payment of process fee and copies within 7 days, and granted six weeks for filing the paper book. In the latest order dated 15.04.2026, two weeks' time was granted to the appellant's counsel to cure default(s) pointed out by the Registry. This case analysis is maintained by casestatus.in based on publicly available court records.