KAMLA CHANDRAKAR vs STATE OF CHHATTISGARH Advocate - A.G., ,FOUZIA MIRZA — WPC/452/2020
Disposed: --DISPOSED OFF on 08th May 2026.
CNR: CGHC010032052020
Filing Number
WPC/1785/2020
Filing Date
23-Jan-2020
Registration No
WPC/452/2020
Registration Date
29-Jan-2020
Judge
Hon'ble Shri Justice Amitendra Kishore Prasad
Coram
Hon'ble Shri Justice Amitendra Kishore Prasad
Bench Type
Single Bench
Category
LAND ACQUISITION & REQUISITION MATTERS ( 5 )
Sub-Category
OTHERS AND MIXED BAG ONES. ( 504 )
Judicial Branch
Writ Section
Decision Date
08-May-2026
Nature of Disposal
--DISPOSED OFF
Last updated 05-Jun-2026
Petitioner(s)
-
1.KAMLA CHANDRAKAR
Adv. Anurag Singh,SHUBHANK TIWARI,SHUBHANK TIWARI, ,MANOJ PARANJPE,VAIBHAV A.GOVERDHAN,Prasoon Agrawal,Bharat Sharma,Rashul bhawnani,VAISHALI MAHILONG,ANSHUL TIWARI,SHUBHANK TIWARI
Respondent(s)
-
1.STATE OF CHHATTISGARH Advocate - A.G., ,FOUZIA MIRZA
-
2.Collector
-
3.Land Acquisition Officer/ Prescribed Officer
-
4.National Highway Authority of India
-
5.Sub Divisional Officer (Revenue)
-
6.National Highway Authority of India
-
7.Tahsildar
Case History
-
Case disposedDisposed
-
08-May-2026
Hon'ble Shri Justice Amitendra Kishore PrasadView PDF
Case Summary: WPC 452/2020 - Kamla Chandrakar v. State of Chhattisgarh The Chhattisgarh High Court allowed multiple petitioners' writ petitions seeking compensation for land acquired under the National Highways Act for the Raipur-Durg bypass project. The court directed the Sub-Divisional Officer to grant petitioners a hearing opportunity regarding compensation entitlement, then refer any disputes to civil court under Section 3H(4) of the Act. While acknowledging that subsequent purchasers cannot challenge acquisition validity, the court held that statutory procedures require fair hearing before compensation determination. This case analysis is maintained by casestatus.in based on publicly available court records.
-
17-Mar-2020
Fresh Matters
Hon'ble Shri Justice P. Sam Koshy
-
31-Jan-2020
Hon'ble Shri Justice P. Sam KoshyView PDF
-
31-Jan-2020
First hearing
Initial hearing scheduled
-
23-Jan-2020
Case filed
Registration No. WPC/452/2020
Case Summary: WPC 452/2020 - Kamla Chandrakar v. State of Chhattisgarh The Chhattisgarh High Court allowed multiple petitioners' writ petitions seeking compensation for land acquired under the National Highways Act for the Raipur-Durg bypass project. The court directed the Sub-Divisional Officer to grant petitioners a hearing opportunity regarding compensation entitlement, then refer any disputes to civil court under Section 3H(4) of the Act. While acknowledging that subsequent purchasers cannot challenge acquisition validity, the court held that statutory procedures require fair hearing before compensation determination. This case analysis is maintained by casestatus.in based on publicly available court records.