SHRI. S.DILLESWAR RAO BANANEE MALLICK vs THE SUPERINTENDING ENGINEER AND ORS. — WPA /132/2026
Case under Electricity Act ,2003 Section NA. Disposed: Contested--DISPOSED on 23rd March 2026.
CNR: WBCHCP0003182026
Filing Number
WPA /132/2026
Filing Date
17-03-2026
Registration No
WPA /132/2026
Registration Date
17-03-2026
Judge
HON'BLE JUSTICE TIRTHANKAR GHOSH
Coram
HON'BLE JUSTICE TIRTHANKAR GHOSH
Bench Type
SINGLE BENCH
Category
GROUP A (WRIT MATTERS) ( 1 )
Sub-Category
Connection/Disconnection ( 1 )
Judicial Branch
Judicial Section
Decision Date
23rd March 2026
Nature of Disposal
Contested--DISPOSED
Acts & Sections
Petitioner(s)
SHRI. S.DILLESWAR RAO BANANEE MALLICK
Respondent(s)
THE SUPERINTENDING ENGINEER AND ORS.
THE EXECUTIVE ENGINEER (HQ)
THE ASSISTANT ENGINEER -I
Hearing History
Judge: HON'BLE JUSTICE TIRTHANKAR GHOSH
ELECTRICITY MATTER
ELECTRICITY MATTER
| Date | Purpose | Result |
|---|---|---|
| 19-03-2026 | ELECTRICITY MATTER | |
| 23-03-2026 | ELECTRICITY MATTER |
Orders
The High Court at Calcutta (Port Blair Circuit Bench) disposed of the petition by directing the Electricity Department to decide the petitioner's electricity connection application dated January 27, 2026, within four weeks in accordance with law. The court found the application was pending without decision and issued a mandamus to expedite the administrative process. This case analysis is maintained by casestatus.in based on publicly available court records.
The High Court at Calcutta (Port Blair Circuit Bench) disposed of the petition by directing the Electricity Department to decide the petitioner's electricity connection application dated January 27, 2026, within four weeks in accordance with law. The court found the application was pending without decision and issued a mandamus to expedite the administrative process. This case analysis is maintained by casestatus.in based on publicly available court records.