UJJWAL ROY K MOHAMMED SHEHEER vs THE SUPERINTENDING ENGINEER AND ANOTHER — WPA/101/2026

Case under Article 226 of Constitution of India Section NA. Next hearing: 16th April 2026.

Next hearing 16-Apr-2026

CNR: WBCHCP0002122026

Filing Number

WPA/101/2026

Filing Date

27-Feb-2026

Registration No

WPA/101/2026

Registration Date

27-Feb-2026

Judge

Hon'ble Justice Chaitali Chatterjee(das)

Coram

Hon'ble Justice Chaitali Chatterjee(das)

Bench Type

SINGLE BENCH

Category

GROUP A (WRIT MATTERS) ( 1 )

Sub-Category

Connection/Disconnection ( 1 )

Judicial Branch

Judicial Section

Last updated 27-Mar-2026

Acts & Sections

Article 226 of Constitution of India Section NA

Petitioner(s)

  1. 1.UJJWAL ROY K MOHAMMED SHEHEER

Respondent(s)

  1. 1.THE SUPERINTENDING ENGINEER AND ANOTHER

  2. 2.THE ASSISTANT ENGINEER

Case History

  1. 16-Apr-2026

    Next hearingPending

  2. 16-Apr-2026

    For Orders

    Hon'ble Justice Chaitali Chatterjee(das)

  3. 23-Mar-2026

    Hon'ble Justice Chaitali Chatterjee(das)View PDF

    Case Summary The petition was adjourned for further hearing. While the respondent authorities confirmed that the electric connection has been provided to the petitioner, the court directed them to file written compliance documentation on the next date of hearing. The matter has been placed before the next Circuit Bench for orders. This case analysis is maintained by casestatus.in based on publicly available court records.

  4. 16-Mar-2026

    Hon'ble Justice Chaitali Chatterjee(das)View PDF

  5. 16-Mar-2026

    Electricity Matter

    Hon'ble Justice Chaitali Chatterjee(das)

  6. 11-Mar-2026

    Hon'ble Justice Chaitali Chatterjee(das)View PDF

  7. 11-Mar-2026

    Electricity Matter

    Hon'ble Justice Chaitali Chatterjee(das)

  8. 10-Mar-2026

    Electricity Matter

    Hon'ble Justice Chaitali Chatterjee(das)

  9. 09-Mar-2026

    Electricity Matter

    Hon'ble Justice Debangsu Basak

  10. 02-Mar-2026

    First hearing

    Initial hearing scheduled

  11. 27-Feb-2026

    Case filed

    Registration No. WPA/101/2026

casestatus.in Summary

Case Summary The petition was adjourned for further hearing. While the respondent authorities confirmed that the electric connection has been provided to the petitioner, the court directed them to file written compliance documentation on the next date of hearing. The matter has been placed before the next Circuit Bench for orders. This case analysis is maintained by casestatus.in based on publicly available court records.