M/S. MEHROTRA BUILDCON PVT. LTD. vs SOUTH EASTERN RAILWAY THROUGH CHIEF ENGINEER, CONSTRUCTION-II, GRC, SOUTH EASTERN RAILWAY — EC-COM/362/2026

Case under Arbitration and Conciliation Act ,1996 Section 36. Next hearing: 16th July 2026.

Next hearing 16-Jul-2026

CNR: WBCHCO0020202026

e-Filing Number

12-06-2026

Filing Number

EC-COM/359/2026

Filing Date

15-Jun-2026

Registration No

EC-COM/362/2026

Registration Date

15-Jun-2026

Judge

Hon'ble Justice Gaurang Kanth

Coram

Hon'ble Justice Gaurang Kanth

Bench Type

Single Bench

Category

GROUP B (CIVIL MATTERS) ( 2 )

Judicial Branch

CURRENT RECORD DEPARTMENT

Last updated 19-Jun-2026

Acts & Sections

Arbitration and Conciliation Act ,1996 Section 36

Petitioner(s)

  1. 1.M/S. MEHROTRA BUILDCON PVT. LTD.

    Adv. Barnik Ghosh

Respondent(s)

  1. 1.SOUTH EASTERN RAILWAY THROUGH CHIEF ENGINEER, CONSTRUCTION-II, GRC, SOUTH EASTERN RAILWAY

Case History

  1. 16-Jul-2026

    Next hearingPending

  2. 16-Jul-2026

    New Chamber Application 1

    Hon'ble Justice Gaurang Kanth

  3. 18-Jun-2026

    Hon'ble Justice Gaurang KanthView PDF

    Case Summary: Mehrotra Buildcon Pvt. Ltd. filed an execution petition in the Calcutta High Court seeking implementation of an arbitral award dated 6 November 2025 against South Eastern Railway. The court admitted the petition as timely filed and directed service upon the railway authority. The award-debtor (South Eastern Railway) was ordered to file an affidavit disclosing full details of movable and immovable properties within three weeks. Matter adjourned to 16 July 2026. This case analysis is maintained by casestatus.in based on publicly available court records.

  4. 18-Jun-2026

    First hearing

    Initial hearing scheduled

  5. 15-Jun-2026

    Case filed

    Registration No. EC-COM/362/2026

casestatus.in Summary

Case Summary: Mehrotra Buildcon Pvt. Ltd. filed an execution petition in the Calcutta High Court seeking implementation of an arbitral award dated 6 November 2025 against South Eastern Railway. The court admitted the petition as timely filed and directed service upon the railway authority. The award-debtor (South Eastern Railway) was ordered to file an affidavit disclosing full details of movable and immovable properties within three weeks. Matter adjourned to 16 July 2026. This case analysis is maintained by casestatus.in based on publicly available court records.