TARAI FOUNDRY WORKS PVT LTD MAYANK ROY vs SHREE KARANI NIRMAN PVT LTD AND ORS — AP/5/2026

Case under Arbitration and Conciliation Act ,1996 Section 11(6). Disposed: Contested--DISPOSED on 22nd May 2026.

Case disposed Next hearing 12-May-2026

CNR: WBCHCJ0018472026

Filing Number

AP/5/2026

Filing Date

08-May-2026

Registration No

AP/5/2026

Registration Date

11-May-2026

Judge

Hon'ble Justice Arindam Mukherjee

Coram

Hon'ble Justice Arindam Mukherjee

Bench Type

Single Bench

Category

GROUP B (CIVIL MATTERS) ( 2 )

Sub-Category

Arbitration ( 2 )

Judicial Branch

RULE SECTION

Decision Date

22-May-2026

Nature of Disposal

Contested--DISPOSED

Last updated 29-May-2026

Acts & Sections

Arbitration and Conciliation Act ,1996 Section 11(6)

Petitioner(s)

  1. 1.TARAI FOUNDRY WORKS PVT LTD MAYANK ROY

Respondent(s)

  1. 1.SHREE KARANI NIRMAN PVT LTD AND ORS

Case History

  1. Case disposedDisposed

  2. 22-May-2026

    Hon'ble Justice Arindam MukherjeeView PDF

    The High Court at Calcutta appointed Mr. Arindam Mitra as sole arbitrator under Section 11(6) of the Arbitration and Conciliation Act, 1996, to resolve the dispute between petitioner Tarai Foundry Works (retired partner) and respondent partnership firm regarding Rs. 1,01,31,326/- owed upon retirement effective December 3, 2025. The arbitration shall proceed at Siliguri with arbitrator fees and expenses borne equally by both parties. This case analysis is maintained by casestatus.in based on publicly available court records.

  3. 22-May-2026

    Arbitration

    Hon'ble Justice Arindam Mukherjee

  4. 19-May-2026

    Hon'ble Justice Arindam MukherjeeView PDF

  5. 19-May-2026

    Arbitration

    Hon'ble Justice Arindam Mukherjee

  6. 12-May-2026

    Hon'ble Justice Arindam MukherjeeView PDF

  7. 12-May-2026

    First hearing

    Initial hearing scheduled

  8. 08-May-2026

    Case filed

    Registration No. AP/5/2026

casestatus.in Summary

The High Court at Calcutta appointed Mr. Arindam Mitra as sole arbitrator under Section 11(6) of the Arbitration and Conciliation Act, 1996, to resolve the dispute between petitioner Tarai Foundry Works (retired partner) and respondent partnership firm regarding Rs. 1,01,31,326/- owed upon retirement effective December 3, 2025. The arbitration shall proceed at Siliguri with arbitrator fees and expenses borne equally by both parties. This case analysis is maintained by casestatus.in based on publicly available court records.

Explore other courts