ASIA PACIFIC GLOBEX PVT. LTD. ARIJIT DEY vs STATE OF WEST BENGAL AND ORS. — WPA/11218/2026
Case under No Act Section NA. Next hearing: 18th June 2026.
CNR: WBCHCA0217572026
Filing Number
WPA/11073/2026
Filing Date
13-May-2026
Registration No
WPA/11218/2026
Registration Date
13-May-2026
Bench Type
Single Bench
Category
GROUP A (WRIT MATTERS) ( 1 )
Sub-Category
Miscellaneous ( 16 )
Judicial Branch
MANDAMUS SECTION
Last updated 29-May-2026
Acts & Sections
Petitioner(s)
-
1.ASIA PACIFIC GLOBEX PVT. LTD. ARIJIT DEY
Respondent(s)
-
1.STATE OF WEST BENGAL AND ORS.
Case History
-
18-Jun-2026
Next hearingPending
-
18-Jun-2026
Specially Fixed Matters
Hon'ble Justice Hiranmay Bhattacharyya
-
21-May-2026
Hon'ble Justice Hiranmay BhattacharyyaView PDF
WPA 11218/2026 Summary: The court granted a stay on the Forest Range Officer's May 11, 2026 eviction notice against Asia Pacific Globex Pvt. Ltd. regarding forest plot No.406 until July 31, 2026. The petitioner undertook not to make further construction or alter the plot's character pending resolution. The case was adjourned to June 18, 2026, with the State required to file an affidavit by June 12, 2026 regarding whether the petitioner has any rights over the 127.46-acre plot or if it remains vested with the Forest Department. This case analysis is maintained by casestatus.in based on publicly available court records.
-
21-May-2026
Specially Fixed Matters
Hon'ble Justice Hiranmay Bhattacharyya
-
20-May-2026
New Motion
Hon'ble Justice Hiranmay Bhattacharyya
-
19-May-2026
Hon'ble Justice Hiranmay BhattacharyyaView PDF
-
19-May-2026
First hearing
Initial hearing scheduled
-
13-May-2026
Case filed
Registration No. WPA/11218/2026
WPA 11218/2026 Summary: The court granted a stay on the Forest Range Officer's May 11, 2026 eviction notice against Asia Pacific Globex Pvt. Ltd. regarding forest plot No.406 until July 31, 2026. The petitioner undertook not to make further construction or alter the plot's character pending resolution. The case was adjourned to June 18, 2026, with the State required to file an affidavit by June 12, 2026 regarding whether the petitioner has any rights over the 127.46-acre plot or if it remains vested with the Forest Department. This case analysis is maintained by casestatus.in based on publicly available court records.