JYOTI SHAW AND ORS. AISHWARYA PRIYA RAHA vs STATE OF WEST BENGAL AND ORS. — WPA/10167/2026

Case under West Bengal Municipal Act ,1993 Section NA. Next hearing: 08th June 2026.

Next hearing 08-Jun-2026

CNR: WBCHCA0195172026

Filing Number

WPA/10066/2026

Filing Date

24-Apr-2026

Registration No

WPA/10167/2026

Registration Date

24-Apr-2026

Bench Type

Single Bench

Category

GROUP A (WRIT MATTERS) ( 1 )

Sub-Category

Miscellaneous ( 12 )

Judicial Branch

MANDAMUS SECTION

Last updated 03-Jun-2026

Acts & Sections

West Bengal Municipal Act ,1993 Section NA

Petitioner(s)

  1. 1.JYOTI SHAW AND ORS. AISHWARYA PRIYA RAHA

Respondent(s)

  1. 1.STATE OF WEST BENGAL AND ORS.

Case History

  1. 08-Jun-2026

    Next hearingPending

  2. 08-Jun-2026

    New Motion - 7

    Hon'ble Justice Raja Basu Chowdhury

  3. 07-May-2026

    Hon'ble Justice Raja Basu ChowdhuryView PDF

    Case Summary: WPA 10167/2026 The petition filed by Jyoti Shaw and others against the State of West Bengal was adjourned. The court granted leave to add Bhatpara Municipality as a respondent and ordered the municipality to conduct an immediate inspection of the disputed property in North 24 Parganas and file a detailed report indicating the extent of construction and whether any sanction was granted. The matter was listed for June 2026, with a clarification that the petition's pendency shall not prevent action against illegal construction. This case analysis is maintained by casestatus.in based on publicly available court records.

  4. 07-May-2026

    First hearing

    Initial hearing scheduled

  5. 07-May-2026

    New Motion - 7

    Hon'ble Justice Raja Basu Chowdhury

  6. 24-Apr-2026

    Case filed

    Registration No. WPA/10167/2026

casestatus.in Summary

Case Summary: WPA 10167/2026 The petition filed by Jyoti Shaw and others against the State of West Bengal was adjourned. The court granted leave to add Bhatpara Municipality as a respondent and ordered the municipality to conduct an immediate inspection of the disputed property in North 24 Parganas and file a detailed report indicating the extent of construction and whether any sanction was granted. The matter was listed for June 2026, with a clarification that the petition's pendency shall not prevent action against illegal construction. This case analysis is maintained by casestatus.in based on publicly available court records.

Explore other courts