MIRA SHAW LAKSHMI SHAW vs WBSEDCL AND ORS — WPA/10160/2026
Case under West Bengal Electricity Act ,2003 Section NA. Next hearing: 09th June 2026.
CNR: WBCHCA0194852026
Filing Number
WPA/10045/2026
Filing Date
23-Apr-2026
Registration No
WPA/10160/2026
Registration Date
23-Apr-2026
Judge
Hon'ble Justice Amrita Sinha
Coram
Hon'ble Justice Amrita Sinha
Bench Type
Single Bench
Category
GROUP A (WRIT MATTERS) ( 1 )
Sub-Category
Connection/Disconnection ( 1 )
Judicial Branch
MANDAMUS SECTION
Last updated 29-May-2026
Acts & Sections
Petitioner(s)
-
1.MIRA SHAW LAKSHMI SHAW
Respondent(s)
-
1.WBSEDCL AND ORS
-
2.DISTRICT ENGINEER AND DISTRICT MANAGER NAIHATI DIVISION
-
3.MR. SURAJIT SEN
-
4.THE POSTMASTER KANKINARA POST OFFICE
-
5.INSPECTOR IN CHARGE BHATPARA POLICE STATION
-
6.BARRACKPORE POLICE COMMISIONERATE
Case History
-
09-Jun-2026
Next hearingPending
-
09-Jun-2026
Assigned Matters
Hon'ble Justice Amrita Sinha
-
22-May-2026
Hon'ble Justice Amrita SinhaView PDF
The High Court at Calcutta adjourned the case to 9th June 2026 after finding that petitioner Mira Shaw had obstructed WBSEDCL inspection officers, detained them for 1.5 hours, and refused meter name transfer from a deceased person's account. The court directed the petitioner to comply with legal procedures for meter transfer and allowed her to file exceptions to the inspection report by 8th June 2026. This case analysis is maintained by casestatus.in based on publicly available court records.
-
22-May-2026
Assigned Matters
Hon'ble Justice Amrita Sinha
-
19-May-2026
Hon'ble Justice Amrita SinhaView PDF
-
11-May-2026
Hon'ble Justice Ravi Krishan KapurView PDF
-
05-May-2026
Hon'ble Justice Ravi Krishan KapurView PDF
-
28-Apr-2026
First hearing
Initial hearing scheduled
-
23-Apr-2026
Case filed
Registration No. WPA/10160/2026
The High Court at Calcutta adjourned the case to 9th June 2026 after finding that petitioner Mira Shaw had obstructed WBSEDCL inspection officers, detained them for 1.5 hours, and refused meter name transfer from a deceased person's account. The court directed the petitioner to comply with legal procedures for meter transfer and allowed her to file exceptions to the inspection report by 8th June 2026. This case analysis is maintained by casestatus.in based on publicly available court records.
Explore other courts