SAKAL DEEP DAS INDRANIL HALDER vs CESC LIMITED AND ORS. — WPA/8668/2026

Case under West Bengal Electricity Act ,2003 Section NA. Disposed: Contested--DISPOSED on 12th May 2026.

Case disposed Next hearing 13-Apr-2026

CNR: WBCHCA0165922026

Filing Number

WPA/8534/2026

Filing Date

07-Apr-2026

Registration No

WPA/8668/2026

Registration Date

07-Apr-2026

Judge

Hon'ble Justice Ravi Krishan Kapur

Coram

Hon'ble Justice Ravi Krishan Kapur

Bench Type

Single Bench

Category

GROUP A (WRIT MATTERS) ( 1 )

Sub-Category

Connection/Disconnection ( 1 )

Judicial Branch

MANDAMUS SECTION

Decision Date

12-May-2026

Nature of Disposal

Contested--DISPOSED

Last updated 21-May-2026

Acts & Sections

West Bengal Electricity Act ,2003 Section NA

Petitioner(s)

  1. 1.SAKAL DEEP DAS INDRANIL HALDER

Respondent(s)

  1. 1.CESC LIMITED AND ORS.

Case History

  1. Case disposedDisposed

  2. 12-May-2026

    Hon'ble Justice Ravi Krishan KapurView PDF

    The court disposed of the writ petition by directing CESC Limited to install a loop meter at the petitioner's premises subject to strengthening the existing electrical service, as per CESC's report dated April 22, 2026. The petitioner must bear all costs and expenses for the work, including any police assistance if required, with completion mandated within four weeks. This case analysis is maintained by casestatus.in based on publicly available court records.

  3. 12-May-2026

    For Hearing

    Hon'ble Justice Ravi Krishan Kapur

  4. 11-May-2026

    Hon'ble Justice Ravi Krishan KapurView PDF

  5. 17-Apr-2026

    Hon'ble Justice Ravi Krishan KapurView PDF

  6. 13-Apr-2026

    Hon'ble Justice Ravi Krishan KapurView PDF

  7. 13-Apr-2026

    First hearing

    Initial hearing scheduled

  8. 07-Apr-2026

    Case filed

    Registration No. WPA/8668/2026

casestatus.in Summary

The court disposed of the writ petition by directing CESC Limited to install a loop meter at the petitioner's premises subject to strengthening the existing electrical service, as per CESC's report dated April 22, 2026. The petitioner must bear all costs and expenses for the work, including any police assistance if required, with completion mandated within four weeks. This case analysis is maintained by casestatus.in based on publicly available court records.