VINOD S/O VITTHAL GULBHELE vs STATE OF MAHARASHTRA, THROUGH ITS SECRETARY, DEPARTMENT OF IRRIGATION, MUMBAI AND ANOTHER Advocate - PURUSHOTTAM PATIL, (FOR R — WP/7803/2018
Case under Project Affected Persons Rehabilitation Act Section U/A226. Disposed: Contested--DISMISSED on 30th March 2026.
CNR: HCBM040266232018
Filing Number
WP/19858/2018
Filing Date
29-Aug-2018
Registration No
WP/7803/2018
Registration Date
15-Nov-2018
Judge
Hon'ble Shri Justice Anil L. Pansare , Hon'ble Justice Nivedita Prakash Mehta
Coram
Hon'ble Shri Justice Anil L. Pansare , Hon'ble Justice Nivedita Prakash Mehta
Bench Type
Division
Category
LAND ACQUISITION/REQUISITION(CENTRAL/STATE) ( 20 )
Sub-Category
OTHERS ( 99 )
Judicial Branch
Civil
Decision Date
30-Mar-2026
Nature of Disposal
Contested--DISMISSED
Last updated 08-Apr-2026
Acts & Sections
Petitioner(s)
-
1.VINOD S/O VITTHAL GULBHELE
Adv. S. W. DESHPANDE,ASHOK P. KHADATKAR,ASHOK P. KHADATKAR, ,ASHOK P. KHADATKAR
Respondent(s)
-
1.STATE OF MAHARASHTRA, THROUGH ITS SECRETARY, DEPARTMENT OF IRRIGATION, MUMBAI AND ANOTHER Advocate - PURUSHOTTAM PATIL, (FOR R
-
2.TAPI PATBANDHARE VIKAS MAHAMANDAL, THR. PRE. PARYAWARAN VISHAYAK LOKASUNAWANI SAMITI and DY. COLLEC
Adv. (FOR R
Case History
-
Case disposedDisposed
-
30-Mar-2026
Hon'ble Shri Justice Anil L. Pansare,hon'ble Justice Nivedita Prakash MehtaView PDF
The Bombay High Court (Nagpur Bench) dismissed 83 consolidated writ petitions filed by landowners seeking enhanced compensation for land acquired under the Kurha Wadhoda irrigation project. The court held that the Supreme Court's judgment in Daulat Sitaram Kodone (relied upon by petitioners) was inapplicable as the facts were substantially different, and that subsequent sale deeds at higher rates were lawfully executed based on government resolutions accounting for price increases. Additionally, the court imposed costs of ₹5,000 per petition, finding that petitioners' counsel had suppressed a prior identical decision dismissing similar claims and attempted to mislead the court. This case analysis is maintained by casestatus.in based on publicly available court records.
-
30-Mar-2026
Fresh Admission-Prioritised Cases/Old Matters
Hon'ble Shri Justice Anil L. Pansare , Hon'ble Justice Nivedita Prakash Mehta
-
24-Mar-2026
Hon'ble Shri Justice Anil L. Pansare,hon'ble Justice Nivedita Prakash MehtaView PDF
-
19-Mar-2021
First hearing
Initial hearing scheduled
-
29-Aug-2018
Case filed
Registration No. WP/7803/2018
The Bombay High Court (Nagpur Bench) dismissed 83 consolidated writ petitions filed by landowners seeking enhanced compensation for land acquired under the Kurha Wadhoda irrigation project. The court held that the Supreme Court's judgment in Daulat Sitaram Kodone (relied upon by petitioners) was inapplicable as the facts were substantially different, and that subsequent sale deeds at higher rates were lawfully executed based on government resolutions accounting for price increases. Additionally, the court imposed costs of ₹5,000 per petition, finding that petitioners' counsel had suppressed a prior identical decision dismissing similar claims and attempted to mislead the court. This case analysis is maintained by casestatus.in based on publicly available court records.