IMAMKHA S/O HUSSAINKHA vs STATE OF MAHARASHTRA, THROUGH ITS SECRETARY, DEPARTMENT OF IRRIGATION, MUMBAI AND ANOTHER Advocate - PURUSHOTTAM PATIL, (FOR R — WP/7775/2018
Case under Project Affected Persons Rehabilitation Act Section U/A226. Disposed: Contested--DISMISSED on 30th March 2026.
CNR: HCBM040236812018
Filing Number
WP/17546/2018
Filing Date
02-Aug-2018
Registration No
WP/7775/2018
Registration Date
15-Nov-2018
Judge
Hon'ble Shri Justice Anil L. Pansare , Hon'ble Justice Nivedita Prakash Mehta
Coram
Hon'ble Shri Justice Anil L. Pansare , Hon'ble Justice Nivedita Prakash Mehta
Bench Type
Division
Category
LAND ACQUISITION/REQUISITION(CENTRAL/STATE) ( 20 )
Sub-Category
OTHERS ( 99 )
Judicial Branch
Civil
Decision Date
30-Mar-2026
Nature of Disposal
Contested--DISMISSED
Last updated 08-Apr-2026
Acts & Sections
Petitioner(s)
-
1.IMAMKHA S/O HUSSAINKHA
Adv. S. W. DESHPANDE,ASHOK P. KHADATKAR,ASHOK P. KHADATKAR, ,ASHOK P. KHADATKAR
Respondent(s)
-
1.STATE OF MAHARASHTRA, THROUGH ITS SECRETARY, DEPARTMENT OF IRRIGATION, MUMBAI AND ANOTHER Advocate - PURUSHOTTAM PATIL, (FOR R
-
2.TAPI IRRIGATION DEVELOPMENT CORPORATION, THROUGH ITS EXECUTIVE DIRECTOR
Case History
-
Case disposedDisposed
-
30-Mar-2026
Hon'ble Shri Justice Anil L. Pansare,hon'ble Justice Nivedita Prakash MehtaView PDF
Summary: The Bombay High Court (Nagpur Bench) dismissed 83 consolidated writ petitions seeking enhanced compensation for land acquired under the Kurha Wadhoda Islampur irrigation project. The court held that the petitioners' reliance on the Supreme Court judgment in Daulat Sitaram Kodone was misplaced, as that case involved fundamentally different facts regarding project-affected persons receiving rehabilitation plots. The court also imposed costs of Rs. 5,000 each on the petitioners for attempting to mislead the court, noting their counsel had previously presented identical arguments before another bench that were already rejected. This case analysis is maintained by casestatus.in based on publicly available court records.
-
30-Mar-2026
Fresh Admission-Prioritised Cases/Old Matters
Hon'ble Shri Justice Anil L. Pansare , Hon'ble Justice Nivedita Prakash Mehta
-
24-Mar-2026
Hon'ble Shri Justice Anil L. Pansare,hon'ble Justice Nivedita Prakash MehtaView PDF
-
24-Mar-2021
First hearing
Initial hearing scheduled
-
02-Aug-2018
Case filed
Registration No. WP/7775/2018
Summary: The Bombay High Court (Nagpur Bench) dismissed 83 consolidated writ petitions seeking enhanced compensation for land acquired under the Kurha Wadhoda Islampur irrigation project. The court held that the petitioners' reliance on the Supreme Court judgment in Daulat Sitaram Kodone was misplaced, as that case involved fundamentally different facts regarding project-affected persons receiving rehabilitation plots. The court also imposed costs of Rs. 5,000 each on the petitioners for attempting to mislead the court, noting their counsel had previously presented identical arguments before another bench that were already rejected. This case analysis is maintained by casestatus.in based on publicly available court records.