NATIONAL HIGHWAYS AUTHORITY OF INDIA THR. PROJECT DIRECTOR, IMPLEMENTATION UNIT- NANDED vs DAGADU VITHOBA JADHAV AND OTHERS — HCBM40155812025

Case under Arbitration and Conciliation Act 1996 Section 34,37.

CNR: HCBM040155812025

e-Filing Number

07-05-2025

Filing Number

AA/11384/2025

Filing Date

08-May-2025

Judge

Registrar (Judicial)

Coram

Registrar (Judicial)

Bench Type

Single

Category

ARBITRATION ( 4 )

Sub-Category

OTHERS ( 99 )

Judicial Branch

Civil

Last updated 18-Jun-2026

Acts & Sections

Arbitration and Conciliation Act 1996 Section 34,37
National Highway Act Section 3G5

Petitioner(s)

  1. 1.NATIONAL HIGHWAYS AUTHORITY OF INDIA THR. PROJECT DIRECTOR, IMPLEMENTATION UNIT- NANDED

    Adv. ANISH ANAND KATHANE

Respondent(s)

  1. 1.DAGADU VITHOBA JADHAV AND OTHERS

  2. 2.COMPETENT AUTHORITY / LAND ACQUISITION, MAHAGAON, YAVATMAL

  3. 3.THE ARBITRATOR / ADDITIONAL COLLECTOR, YAVATMAL

  4. 4.THE STATE OF MAHARASHTRA, THR. COLLECTOR, YAVATMAL

  5. 5.THE STATE OF MAHARASHTRA, THR. NHAI, MUMBAI

Case History

  1. 08-Jun-2026

    For Orders -

    Registrar (Judicial)

  2. 07-May-2026

    Registrar (Judicial)View PDF

    In this Arbitration Appeal before the Bombay High Court at Nagpur, the National Highways Authority of India challenged an arbitrator's award in a land acquisition dispute with Dagadu Vithoba Jadhav and others. The court adjourned the matter on May 7, 2026, granting the parties two weeks as a final opportunity to comply with procedural requirements before substantive hearing. This case analysis is maintained by casestatus.in based on publicly available court records.

  3. 23-Mar-2026

    For Orders -

    Registrar (Judicial)

  4. 05-Mar-2026

    Registrar (Judicial)View PDF

  5. 04-Dec-2025

    For Orders

    Registrar (Judicial)

  6. 20-Nov-2025

    Registrar (Judicial)View PDF

  7. 20-Nov-2025

    First hearing

    Initial hearing scheduled

  8. 08-May-2025

    Case filed

casestatus.in Summary

In this Arbitration Appeal before the Bombay High Court at Nagpur, the National Highways Authority of India challenged an arbitrator's award in a land acquisition dispute with Dagadu Vithoba Jadhav and others. The court adjourned the matter on May 7, 2026, granting the parties two weeks as a final opportunity to comply with procedural requirements before substantive hearing. This case analysis is maintained by casestatus.in based on publicly available court records.

Explore other courts