M/S SHANTI CONSTRUCTIONS, THR. AUTHORISED SIGNATORY, ANKUR RUPCHAND KHANDELWAL vs THE STATE OF MAHARASHTRA, THR. SUPERINTENDING ENGINEER, PUBIC WORKS CIRCLE DEPT., AKOLA AND OTHERS — WP/3071/2026

Case under Constitution of India Section 226. Next hearing: 11th June 2026.

CNR: HCBM040111872026

Next Hearing

11th June 2026

Filing Number

WP/7659/2026

Filing Date

30-03-2026

Registration No

WP/3071/2026

Registration Date

15-04-2026

Judge

HON'BLE JUSTICE URMILA JOSHI PHALKE , HON'BLE JUSTICE NIVEDITA PRAKASH MEHTA

Coram

HON'BLE JUSTICE URMILA JOSHI PHALKE , HON'BLE JUSTICE NIVEDITA PRAKASH MEHTA

Bench Type

Division

Category

TENDER MATTERS ( 44 )

Judicial Branch

Civil

Acts & Sections

Constitution of India Section 226
Other Act
Public Works Dept Act

Petitioner(s)

M/S SHANTI CONSTRUCTIONS, THR. AUTHORISED SIGNATORY, ANKUR RUPCHAND KHANDELWAL

Adv. KARTIK N SHUKUL,VIKRANT M. VISHWARUPE,VIKRANT M. VISHWARUPE, ,VIKRANT M. VISHWARUPE

Respondent(s)

THE STATE OF MAHARASHTRA, THR. SUPERINTENDING ENGINEER, PUBIC WORKS CIRCLE DEPT., AKOLA AND OTHERS

THE EXECUTIVE ENGINEER, PUBLIC WORKS DIVISION, AKOLA

THE SENIOR DIVISIONAL ACCOUNTS OFFICER, PUBLIC WORKS DIVISION, AKOLA

M/S A.M. KOTHARI, AKOLA

M/S OBEROI CONSTRUCTION, AKOLA

PRABH ENGINEER, AKOLA

Hearing History

Judge: HON'BLE JUSTICE URMILA JOSHI PHALKE , HON'BLE JUSTICE NIVEDITA PRAKASH MEHTA

28-04-2026
11-06-2026

FOR ADMISSION - AT 2.30 P.M. (CIVIL SIDE MATTERS)

30-04-2026

FOR ORDERS(CIVIL SIDE MATTERS) AT 2.30 P.M.

22-04-2026

ADMISSION {AT 2.30 pm}

Orders

30-04-2026
HON'BLE JUSTICE URMILA JOSHI PHALKE,HON'BLE JUSTICE NIVEDITA PRAKASH MEHTA

Summary: A bunch of eight related writ petitions filed by construction companies (Veer Hanumanji Construction and Shanti Constructions) against the State of Maharashtra were heard in part by the Nagpur Bench of Bombay High Court on 30th April, 2026. The Court adjourned the cases as "part heard" and listed them for further hearing on 11.06.2026, with any interim orders continuing until the next date. This case analysis is maintained by casestatus.in based on publicly available court records.

casestatus.in Summary

Summary: A bunch of eight related writ petitions filed by construction companies (Veer Hanumanji Construction and Shanti Constructions) against the State of Maharashtra were heard in part by the Nagpur Bench of Bombay High Court on 30th April, 2026. The Court adjourned the cases as "part heard" and listed them for further hearing on 11.06.2026, with any interim orders continuing until the next date. This case analysis is maintained by casestatus.in based on publicly available court records.

Browse Related Cases

Explore other courts

Search Another Case