DEPUTY CHIEF ENGINEER (CONSTRUCTION) CENTRAL RAILWAY, AJNI, NAGPUR vs SHRI. VILAS S/O SHANKARRAO JOSHI AND OTHERS Advocate - VAIBHAV N PATRE, VAIBHAV N PATRE (FOR R/ — FA/316/2026
Case under Land Acquisition Act Section 54 R/W 96. Next hearing: 23rd May 2026.
CNR: HCBM040091362025
Filing Number
FA/6623/2025
Filing Date
20-Mar-2025
Registration No
FA/316/2026
Registration Date
30-Apr-2026
Bench Type
Single
Category
LAND ACQUISITION/REQUISITION(CENTRAL/STATE) ( 20 )
Sub-Category
COMPENSATION ( 8 )
Judicial Branch
Civil
Last updated 28-May-2026
Acts & Sections
Petitioner(s)
-
1.DEPUTY CHIEF ENGINEER (CONSTRUCTION) CENTRAL RAILWAY, AJNI, NAGPUR
Adv. VANDAN M. GADKARI,ABHISHEK PANDURANG NARWADIYA,ABHISHEK PANDURANG NARWADIYA, ,AKASH P. JOSHI,NIRAJ R. TIKNAYAT,ABHISHEK PANDURANG NARWADIYA
Respondent(s)
-
1.SHRI. VILAS S/O SHANKARRAO JOSHI AND OTHERS Advocate - VAIBHAV N PATRE, VAIBHAV N PATRE (FOR R/
-
2.,PUNAM DILIPRAO PISURDE (FOR R/
-
3.,GOVERNMENT PLEADER (FOR R/2 AND
-
4.THE STATE OF MAHARASHTRA, THR. COLLECTOR, WARDHA
-
5.SPECIAL LAND ACQUISITION OFFICER, UPPER WARDHA PROJECT, WARDHA
Case History
-
23-May-2026
Next hearingPending
-
23-May-2026
—
-
17-Apr-2026
Hon'ble Shri Justice Yanshivraj Gopichand KhobragadeView PDF
Case Summary: FA/316/2026 The High Court of Bombay (Nagpur Bench) heard three applications on 17 April 2026. The court condoned a 1017-day delay in filing the statutory appeal by the Deputy Chief Engineer (Central Railway) upon payment of Rs. 3,000 costs, citing unintentional delay during Covid-19 and approval procedures. The respondent was permitted to withdraw 75% of the deposited compensation (50% with undertaking, 25% with surety). The First Appeal (ST) No. 6623/2025 was admitted on merits, with records called and the appellant directed to file the private paper book within eight weeks. This case analysis is maintained by casestatus.in based on publicly available court records.
-
20-Mar-2025
Case filed
Registration No. FA/316/2026
Case Summary: FA/316/2026 The High Court of Bombay (Nagpur Bench) heard three applications on 17 April 2026. The court condoned a 1017-day delay in filing the statutory appeal by the Deputy Chief Engineer (Central Railway) upon payment of Rs. 3,000 costs, citing unintentional delay during Covid-19 and approval procedures. The respondent was permitted to withdraw 75% of the deposited compensation (50% with undertaking, 25% with surety). The First Appeal (ST) No. 6623/2025 was admitted on merits, with records called and the appellant directed to file the private paper book within eight weeks. This case analysis is maintained by casestatus.in based on publicly available court records.
Explore other courts