DEPUTY CHIEF ENGINEER (CONSTRUCTION) CENTRAL RAILWAY, AJNI, NAGPUR vs SHRI. VILAS S/O SHANKARRAO JOSHI AND OTHERS Advocate - VAIBHAV N PATRE, VAIBHAV N PATRE (FOR R/ — FA/316/2026

Case under Land Acquisition Act Section 54 R/W 96. Next hearing: 23rd May 2026.

Next hearing 23-May-2026

CNR: HCBM040091362025

Filing Number

FA/6623/2025

Filing Date

20-Mar-2025

Registration No

FA/316/2026

Registration Date

30-Apr-2026

Bench Type

Single

Category

LAND ACQUISITION/REQUISITION(CENTRAL/STATE) ( 20 )

Sub-Category

COMPENSATION ( 8 )

Judicial Branch

Civil

Last updated 28-May-2026

Acts & Sections

Land Acquisition Act Section 54 R/W 96
Indian Evidence Act
Limitation Act,1963

Petitioner(s)

  1. 1.DEPUTY CHIEF ENGINEER (CONSTRUCTION) CENTRAL RAILWAY, AJNI, NAGPUR

    Adv. VANDAN M. GADKARI,ABHISHEK PANDURANG NARWADIYA,ABHISHEK PANDURANG NARWADIYA, ,AKASH P. JOSHI,NIRAJ R. TIKNAYAT,ABHISHEK PANDURANG NARWADIYA

Respondent(s)

  1. 1.SHRI. VILAS S/O SHANKARRAO JOSHI AND OTHERS Advocate - VAIBHAV N PATRE, VAIBHAV N PATRE (FOR R/

  2. 2.,PUNAM DILIPRAO PISURDE (FOR R/

  3. 3.,GOVERNMENT PLEADER (FOR R/2 AND

  4. 4.THE STATE OF MAHARASHTRA, THR. COLLECTOR, WARDHA

  5. 5.SPECIAL LAND ACQUISITION OFFICER, UPPER WARDHA PROJECT, WARDHA

Case History

  1. 23-May-2026

    Next hearingPending

  2. 23-May-2026

  3. 17-Apr-2026

    Hon'ble Shri Justice Yanshivraj Gopichand KhobragadeView PDF

    Case Summary: FA/316/2026 The High Court of Bombay (Nagpur Bench) heard three applications on 17 April 2026. The court condoned a 1017-day delay in filing the statutory appeal by the Deputy Chief Engineer (Central Railway) upon payment of Rs. 3,000 costs, citing unintentional delay during Covid-19 and approval procedures. The respondent was permitted to withdraw 75% of the deposited compensation (50% with undertaking, 25% with surety). The First Appeal (ST) No. 6623/2025 was admitted on merits, with records called and the appellant directed to file the private paper book within eight weeks. This case analysis is maintained by casestatus.in based on publicly available court records.

  4. 20-Mar-2025

    Case filed

    Registration No. FA/316/2026

casestatus.in Summary

Case Summary: FA/316/2026 The High Court of Bombay (Nagpur Bench) heard three applications on 17 April 2026. The court condoned a 1017-day delay in filing the statutory appeal by the Deputy Chief Engineer (Central Railway) upon payment of Rs. 3,000 costs, citing unintentional delay during Covid-19 and approval procedures. The respondent was permitted to withdraw 75% of the deposited compensation (50% with undertaking, 25% with surety). The First Appeal (ST) No. 6623/2025 was admitted on merits, with records called and the appellant directed to file the private paper book within eight weeks. This case analysis is maintained by casestatus.in based on publicly available court records.

Explore other courts

Search Another Case