DEPUTY CHIEF ENGINEER (CONSTRUCTION) CENTRAL RAILWAY, AJNI, NAGPUR vs SHRI. VILAS S/O SHANKARRAO JOSHI AND OTHERS Advocate - VAIBHAV N PATRE, VAIBHAV N PATRE (FOR R/ — FA/316/2026

Case under Land Acquisition Act Section 54 R/W 96. Next hearing: 23rd May 2026.

CNR: HCBM040091362025

Next Hearing

23rd May 2026

Filing Number

FA/6623/2025

Filing Date

20-03-2025

Registration No

FA/316/2026

Registration Date

30-04-2026

Bench Type

Single

Category

LAND ACQUISITION/REQUISITION(CENTRAL/STATE) ( 20 )

Sub-Category

COMPENSATION ( 8 )

Judicial Branch

Civil

Acts & Sections

Land Acquisition Act Section 54 R/W 96
Indian Evidence Act Section ---
Limitation Act,1963 Section ---

Petitioner(s)

DEPUTY CHIEF ENGINEER (CONSTRUCTION) CENTRAL RAILWAY, AJNI, NAGPUR

Adv. VANDAN M. GADKARI,ABHISHEK PANDURANG NARWADIYA,ABHISHEK PANDURANG NARWADIYA, ,AKASH P. JOSHI,NIRAJ R. TIKNAYAT,ABHISHEK PANDURANG NARWADIYA

Respondent(s)

SHRI. VILAS S/O SHANKARRAO JOSHI AND OTHERS Advocate - VAIBHAV N PATRE, VAIBHAV N PATRE (FOR R/

,PUNAM DILIPRAO PISURDE (FOR R/

,GOVERNMENT PLEADER (FOR R/2 AND

THE STATE OF MAHARASHTRA, THR. COLLECTOR, WARDHA

SPECIAL LAND ACQUISITION OFFICER, UPPER WARDHA PROJECT, WARDHA

Hearing History

23-05-2026

Orders

17-04-2026
HON'BLE SHRI JUSTICE YANSHIVRAJ GOPICHAND KHOBRAGADE

Case Summary: FA/316/2026 The High Court of Bombay (Nagpur Bench) heard three applications on 17 April 2026. The court condoned a 1017-day delay in filing the statutory appeal by the Deputy Chief Engineer (Central Railway) upon payment of Rs. 3,000 costs, citing unintentional delay during Covid-19 and approval procedures. The respondent was permitted to withdraw 75% of the deposited compensation (50% with undertaking, 25% with surety). The First Appeal (ST) No. 6623/2025 was admitted on merits, with records called and the appellant directed to file the private paper book within eight weeks. This case analysis is maintained by casestatus.in based on publicly available court records.

casestatus.in Summary

Case Summary: FA/316/2026 The High Court of Bombay (Nagpur Bench) heard three applications on 17 April 2026. The court condoned a 1017-day delay in filing the statutory appeal by the Deputy Chief Engineer (Central Railway) upon payment of Rs. 3,000 costs, citing unintentional delay during Covid-19 and approval procedures. The respondent was permitted to withdraw 75% of the deposited compensation (50% with undertaking, 25% with surety). The First Appeal (ST) No. 6623/2025 was admitted on merits, with records called and the appellant directed to file the private paper book within eight weeks. This case analysis is maintained by casestatus.in based on publicly available court records.

Browse Related Cases

Explore other courts

Search Another Case