DEPUTY CHIEF ENGINEER (CONSTRUCTION) CENTRAL RAILWAY, AJNI, NAGPUR vs SHRI. VILAS S/O SHANKARRAO JOSHI AND OTHERS Advocate - VAIBHAV N PATRE, VAIBHAV N PATRE (FOR R/ — FA/316/2026
Case under Land Acquisition Act Section 54 R/W 96. Next hearing: 23rd May 2026.
CNR: HCBM040091362025
Next Hearing
23rd May 2026
Filing Number
FA/6623/2025
Filing Date
20-03-2025
Registration No
FA/316/2026
Registration Date
30-04-2026
Bench Type
Single
Category
LAND ACQUISITION/REQUISITION(CENTRAL/STATE) ( 20 )
Sub-Category
COMPENSATION ( 8 )
Judicial Branch
Civil
Acts & Sections
Petitioner(s)
DEPUTY CHIEF ENGINEER (CONSTRUCTION) CENTRAL RAILWAY, AJNI, NAGPUR
Adv. VANDAN M. GADKARI,ABHISHEK PANDURANG NARWADIYA,ABHISHEK PANDURANG NARWADIYA, ,AKASH P. JOSHI,NIRAJ R. TIKNAYAT,ABHISHEK PANDURANG NARWADIYA
Respondent(s)
SHRI. VILAS S/O SHANKARRAO JOSHI AND OTHERS Advocate - VAIBHAV N PATRE, VAIBHAV N PATRE (FOR R/
,PUNAM DILIPRAO PISURDE (FOR R/
,GOVERNMENT PLEADER (FOR R/2 AND
THE STATE OF MAHARASHTRA, THR. COLLECTOR, WARDHA
SPECIAL LAND ACQUISITION OFFICER, UPPER WARDHA PROJECT, WARDHA
Hearing History
| Date | Purpose |
|---|---|
| 23-05-2026 |
Orders
Case Summary: FA/316/2026 The High Court of Bombay (Nagpur Bench) heard three applications on 17 April 2026. The court condoned a 1017-day delay in filing the statutory appeal by the Deputy Chief Engineer (Central Railway) upon payment of Rs. 3,000 costs, citing unintentional delay during Covid-19 and approval procedures. The respondent was permitted to withdraw 75% of the deposited compensation (50% with undertaking, 25% with surety). The First Appeal (ST) No. 6623/2025 was admitted on merits, with records called and the appellant directed to file the private paper book within eight weeks. This case analysis is maintained by casestatus.in based on publicly available court records.
Case Summary: FA/316/2026 The High Court of Bombay (Nagpur Bench) heard three applications on 17 April 2026. The court condoned a 1017-day delay in filing the statutory appeal by the Deputy Chief Engineer (Central Railway) upon payment of Rs. 3,000 costs, citing unintentional delay during Covid-19 and approval procedures. The respondent was permitted to withdraw 75% of the deposited compensation (50% with undertaking, 25% with surety). The First Appeal (ST) No. 6623/2025 was admitted on merits, with records called and the appellant directed to file the private paper book within eight weeks. This case analysis is maintained by casestatus.in based on publicly available court records.
Browse Related Cases
Cases under same legislation
Explore other courts