V.I.D.C., THR. EXECUTIVE ENGINEER, JIGAON PROJECT, SHEGAON vs DEVIDAS BALIRAM SABE AND OTHERS — FA/344/2026
Case under Right to Fair Compensation & Transparency in Land Acquisition,rehabilitation & Resettlement Act,2013 Section 74. Next hearing: 13th June 2026.
CNR: HCBM040014052026
Filing Number
FA/1037/2026
Filing Date
14-Jan-2026
Registration No
FA/344/2026
Registration Date
15-May-2026
Bench Type
Single
Category
LAND ACQUISITION/REQUISITION(CENTRAL/STATE) ( 20 )
Sub-Category
COMPENSATION ( 8 )
Judicial Branch
Civil
Last updated 18-Jun-2026
Acts & Sections
Petitioner(s)
-
1.V.I.D.C., THR. EXECUTIVE ENGINEER, JIGAON PROJECT, SHEGAON
Adv. SK BHOYAR,PRANAV A. PAWADE,PRANAV A. PAWADE, ,PRANAV A. PAWADE
Respondent(s)
-
1.DEVIDAS BALIRAM SABE AND OTHERS
Adv. SHIVANSH S. DALVI (FOR R/
-
2.,HARIOM V. DHAGE (FOR R/
-
3.1123
-
4.THE STATE OF MAHARASHTRA, THR. ITS COLLECTOR, BULDHANA
-
5.SPECIAL LAND ACQUISITION OFFICER, MINOR IRRIGATION WORKS, JIGAON PROJECT, BULDHANA
Case History
-
13-Jun-2026
Next hearingPending
-
13-Jun-2026
—
-
07-May-2026
Hon'ble Shri Justice Yanshivraj Gopichand KhobragadeView PDF
Case Summary: CAF No.1507/2026 The High Court of Bombay (Nagpur Bench) allowed VIDC's condonation application for a 59-day delay in filing its appeal against a Land Acquisition Authority judgment dated 05/08/2025. The First Appeal (St.No.1037/2026) was admitted, with the appellant ordered to file a paper-book within 12 weeks. Additionally, in CAF No.1712/2026, the original claimant was permitted to withdraw 75% of awarded compensation upon furnishing an undertaking to the court's Registrar. This case analysis is maintained by casestatus.in based on publicly available court records.
-
14-Jan-2026
Case filed
Registration No. FA/344/2026
Case Summary: CAF No.1507/2026 The High Court of Bombay (Nagpur Bench) allowed VIDC's condonation application for a 59-day delay in filing its appeal against a Land Acquisition Authority judgment dated 05/08/2025. The First Appeal (St.No.1037/2026) was admitted, with the appellant ordered to file a paper-book within 12 weeks. Additionally, in CAF No.1712/2026, the original claimant was permitted to withdraw 75% of awarded compensation upon furnishing an undertaking to the court's Registrar. This case analysis is maintained by casestatus.in based on publicly available court records.