The Executive Engineer (Medium Project Division), Osmanabad and others ADV SUNITA DASHRATHRAO SHELKE vs Dattu Dagdu Pawar (Died) T/h L.Rs. Kusum Dattu Pawar and others 1. — CA/13667/2025

Case under Land Acquisition Act - Appeal Section 54. Disposed: --Admitted/Allowed/Granted/Rule Absolute on 05th May 2026.

Case disposed

CNR: HCBM030493942025

e-Filing Number

26-11-2025

Filing Number

CA/36493/2025

Filing Date

07-Dec-2025

Registration No

CA/13667/2025

Registration Date

10-Dec-2025

Judge

Hon'ble Shri Justice Shailesh P. Brahme

Coram

Hon'ble Shri Justice Shailesh P. Brahme

Bench Type

Single

Judicial Branch

Civil

Decision Date

05-May-2026

Nature of Disposal

--Admitted/Allowed/Granted/Rule Absolute

Last updated 15-Jun-2026

Acts & Sections

Land Acquisition Act - Appeal Section 54

Petitioner(s)

  1. 1.The Executive Engineer (Medium Project Division), Osmanabad and others ADV SUNITA DASHRATHRAO SHELKE

  2. 2.The Special Land Acquisition Officer

  3. 3.The State of Maharashtra, Through The Collector

Respondent(s)

  1. 1.Dattu Dagdu Pawar (Died) T/h L.Rs. Kusum Dattu Pawar and others 1.

  2. 2.Kusum W/o Dattu Pawar

    Adv. R.NO. 1,2,4 AND 5 SERVED1.

  3. 3.Subhash S/o Dattu Pawar1.

  4. 4.Sunita W/o Baba Bhosale1.

  5. 5.Maina W/o Pandurang Kaldate1.

  6. 6.Rani D/o Dattu Pawar

Case History

  1. Case disposedDisposed

  2. 05-May-2026

    Hon'ble Shri Justice Shailesh P. BrahmeView PDF

    Summary of CA/13667/2025 The High Court of Bombay (Aurangabad Bench) partly allowed the Executive Engineer's appeals in land acquisition cases, modifying the Reference Court's awards on interest calculation. The court held that interest under Sections 28 and 34 of the Land Acquisition Act is payable from the date of award (not from notification), following the Full Bench precedent in State of Maharashtra v. Kailash Shiva Rangari. Deposited amounts with accrued interest were ordered disbursed to claimants accordingly. This case analysis is maintained by casestatus.in based on publicly available court records.

  3. 05-May-2026

    For Orders

    Hon'ble Shri Justice Shailesh P. Brahme

  4. 15-Apr-2026

    For Orders

    Hon'ble Shri Justice Shailesh P. Brahme

  5. 17-Mar-2026

    For Orders

    Hon'ble Shri Justice Shailesh P. Brahme

  6. 03-Feb-2026

    Hon'ble Shri Justice Shailesh P. BrahmeView PDF

  7. 03-Feb-2026

    First hearing

    Initial hearing scheduled

  8. 05-Jan-2026

    Hon'ble Shri Justice Shailesh P. BrahmeView PDF

  9. 16-Dec-2025

    Hon'ble Shri Justice Shailesh P. BrahmeView PDF

  10. 16-Dec-2025

    Hon'ble Shri Justice Shailesh P. BrahmeView PDF

  11. 07-Dec-2025

    Case filed

    Registration No. CA/13667/2025

casestatus.in Summary

Summary of CA/13667/2025 The High Court of Bombay (Aurangabad Bench) partly allowed the Executive Engineer's appeals in land acquisition cases, modifying the Reference Court's awards on interest calculation. The court held that interest under Sections 28 and 34 of the Land Acquisition Act is payable from the date of award (not from notification), following the Full Bench precedent in State of Maharashtra v. Kailash Shiva Rangari. Deposited amounts with accrued interest were ordered disbursed to claimants accordingly. This case analysis is maintained by casestatus.in based on publicly available court records.

Explore other courts

Search Another Case