UNION OF INDIA THROUGH THE GENERAL MANAGER CENTRAL RAILWAY vs UDHAV S/O RAMBHAU PHAD AND ANR — FA/388/2026

Case under Land Acquisition Act - Appeal Section 96CPC. Disposed: Contested--DISMISSED on 18th April 2026.

Case disposed

CNR: HCBM030483192023

e-Filing Number

21-11-2023

Filing Number

FA/36437/2023

Filing Date

21-Nov-2023

Registration No

FA/388/2026

Registration Date

09-Feb-2026

Judge

Hon'ble Shri Justice Shailesh P. Brahme

Coram

Hon'ble Shri Justice Shailesh P. Brahme

Bench Type

Single

Judicial Branch

Civil

Decision Date

18-Apr-2026

Nature of Disposal

Contested--DISMISSED

Last updated 15-Jun-2026

Acts & Sections

Land Acquisition Act - Appeal Section 96CPC

Petitioner(s)

  1. 1.UNION OF INDIA THROUGH THE GENERAL MANAGER CENTRAL RAILWAY

    Adv. Talhar Ajay G.

  2. 2.THE DEPUTY CHIEF ENGINEER, CONSTRUCTION, CENTRAL RAILWAY

  3. 3.THE STATE OF MAHARASHTRA, THROUGH THE COLLECTOR

  4. 4.THE DEPUTY COLLECTOR (LAND ACQUISITION), JAYKWADI PROJECT, BEED

Respondent(s)

  1. 1.UDHAV S/O RAMBHAU PHAD AND ANR

  2. 2.SUSEN RAMBHAU PHAD

  3. 3.SOMNATH S/O RAMBHAU PHAD

  4. 4.MACCHINDRA S/O REKHU CHAVAN

Case History

  1. Case disposedDisposed

  2. 04-May-2026

    Hon'ble Shri Justice Shailesh P. BrahmeView PDF

    Case Summary: FA/388/2026 The High Court of Bombay at Aurangabad dismissed the Union of India's appeals challenging the Reference Court's enhancement of land compensation for acquisition of properties in Ghatsawali village for the Ahmednagar-Beed-Parli railway project. The court upheld the Reference Court's award of Rs. 4,000-6,000 per Rupee (against the initial Rs. 1,180 per R), finding the rate reasonable and supported by compatible sale deed evidence (Exhibit 28), and confirmed statutory benefits under Section 23(1-A) of the Land Acquisition Act with accrued interest as lawful. This case analysis is maintained by casestatus.in based on publicly available court records.

  3. 30-Mar-2026

    For Orders

    Hon'ble Shri Justice Shailesh P. Brahme

  4. 05-Mar-2026

    Hon'ble Shri Justice Shailesh P. BrahmeView PDF

  5. 05-Mar-2026

    For Orders

    Hon'ble Shri Justice Shailesh P. Brahme

  6. 12-Feb-2026

    Hon'ble Shri Justice Shailesh P. BrahmeView PDF

  7. 12-Feb-2026

    First hearing

    Initial hearing scheduled

  8. 21-Nov-2023

    Case filed

    Registration No. FA/388/2026

casestatus.in Summary

Case Summary: FA/388/2026 The High Court of Bombay at Aurangabad dismissed the Union of India's appeals challenging the Reference Court's enhancement of land compensation for acquisition of properties in Ghatsawali village for the Ahmednagar-Beed-Parli railway project. The court upheld the Reference Court's award of Rs. 4,000-6,000 per Rupee (against the initial Rs. 1,180 per R), finding the rate reasonable and supported by compatible sale deed evidence (Exhibit 28), and confirmed statutory benefits under Section 23(1-A) of the Land Acquisition Act with accrued interest as lawful. This case analysis is maintained by casestatus.in based on publicly available court records.