National Highways Authority of India PIU, Nanded thru. its Project Director Swapnil Kasar DESHMUKH VAIBHAV PURUSHOTTAM vs Harishchandra Venkatrao Birle and Ors. — CA/13165/2025
Case under Arbitration Act 1940 Section 37. Disposed: --DISPOSED OFF on 01st April 2026.
CNR: HCBM030475032025
e-Filing Number
29-04-2025
Filing Number
CA/35122/2025
Filing Date
24-Nov-2025
Registration No
CA/13165/2025
Registration Date
28-Nov-2025
Judge
Hon'ble Shri Justice Arun R. Pedneker
Coram
Hon'ble Shri Justice Arun R. Pedneker
Bench Type
Single
Judicial Branch
Civil
Decision Date
01-Apr-2026
Nature of Disposal
--DISPOSED OFF
Last updated 08-May-2026
Acts & Sections
Petitioner(s)
-
1.National Highways Authority of India PIU, Nanded thru. its Project Director Swapnil Kasar DESHMUKH VAIBHAV PURUSHOTTAM
Respondent(s)
-
1.Harishchandra Venkatrao Birle and Ors.
-
2.The Competent Authority Land Acquisition
-
3.The Arbitrator And Dist Collector Latur
Case History
-
Case disposedDisposed
-
01-Apr-2026
Hon'ble Shri Justice Arun R. PednekerView PDF
The High Court of Bombay at Aurangabad allowed NHAI's appeal against the District Judge's rejection of delay condonation for filing a Section 34 application under the Arbitration and Conciliation Act. The court found the District Judge was mistaken in calculating a five-month delay, when the application was actually filed within 120 days (with only 24 days' actual delay beyond statutory requirement), thus deserving condonation. The matter was remitted to the District Court to decide the Section 34 application on merits within three months. This case analysis is maintained by casestatus.in based on publicly available court records.
-
01-Apr-2026
For Orders
Hon'ble Shri Justice Arun R. Pedneker
-
13-Mar-2026
For Orders
Hon'ble Shri Justice Sachin S. Deshmukh
-
20-Feb-2026
For Orders
Hon'ble Shri Justice Sachin S. Deshmukh
-
23-Jan-2026
For Orders
Hon'ble Shri Justice Sachin S. Deshmukh
-
09-Jan-2026
For Orders
Hon'ble Shri Justice Arun R. Pedneker
-
17-Dec-2025
First hearing
Initial hearing scheduled
-
24-Nov-2025
Case filed
Registration No. CA/13165/2025
The High Court of Bombay at Aurangabad allowed NHAI's appeal against the District Judge's rejection of delay condonation for filing a Section 34 application under the Arbitration and Conciliation Act. The court found the District Judge was mistaken in calculating a five-month delay, when the application was actually filed within 120 days (with only 24 days' actual delay beyond statutory requirement), thus deserving condonation. The matter was remitted to the District Court to decide the Section 34 application on merits within three months. This case analysis is maintained by casestatus.in based on publicly available court records.