UNION OF INDIA THROUGH THE GENERAL MANAGER CENTRAL RAILWAY AND ORS vs DADARAO PANDURANG PHAD — FA/390/2026
Case under Land Acquisition Act - Appeal Section 18. Disposed: --DISMISSED on 04th May 2026.
CNR: HCBM030388812023
e-Filing Number
13-09-2023
Filing Number
FA/29236/2023
Filing Date
13-Sep-2023
Registration No
FA/390/2026
Registration Date
09-Feb-2026
Judge
Hon'ble Shri Justice Shailesh P. Brahme
Coram
Hon'ble Shri Justice Shailesh P. Brahme
Bench Type
Single
Judicial Branch
Civil
Decision Date
04-May-2026
Nature of Disposal
--DISMISSED
Last updated 15-Jun-2026
Acts & Sections
Petitioner(s)
-
1.UNION OF INDIA THROUGH THE GENERAL MANAGER CENTRAL RAILWAY AND ORS
Adv. Talhar Ajay G.
-
2.THE DEPUTY CHIEF ENGINEER CONSTRUCTION CENTRAL RAILWAY
-
3.THE STATE OF MAHARASHTRA THROUGH THE COLLECTOR BEED
-
4.THE DEPUTYC COLLECTOR LAND ACQUISITION JAYAKWADI PROJECT BEED TQ DIST BEED
Respondent(s)
-
1.DADARAO PANDURANG PHAD
Case History
-
Case disposedDisposed
-
04-May-2026
Hon'ble Shri Justice Shailesh P. BrahmeView PDF
Case Summary: FA/390/2026 The High Court of Bombay (Aurangabad Bench) dismissed the Union of India's appeal challenging a Reference Court's enhanced land compensation award for properties acquired for a railway project in Beed district. The Reference Court had increased rates from Rs. 980-1,180 per rupee to Rs. 4,000 per rupee based on comparable sale deeds from the same village, which the High Court found reasonable and supported by credible evidence. The court upheld statutory benefits including solatium and interest under applicable law. This case analysis is maintained by casestatus.in based on publicly available court records.
-
30-Mar-2026
For Orders
Hon'ble Shri Justice Shailesh P. Brahme
-
05-Mar-2026
Hon'ble Shri Justice Shailesh P. BrahmeView PDF
-
05-Mar-2026
For Orders
Hon'ble Shri Justice Shailesh P. Brahme
-
12-Feb-2026
Hon'ble Shri Justice Shailesh P. BrahmeView PDF
-
28-Nov-2023
First hearing
Initial hearing scheduled
-
13-Sep-2023
Case filed
Registration No. FA/390/2026
Case Summary: FA/390/2026 The High Court of Bombay (Aurangabad Bench) dismissed the Union of India's appeal challenging a Reference Court's enhanced land compensation award for properties acquired for a railway project in Beed district. The Reference Court had increased rates from Rs. 980-1,180 per rupee to Rs. 4,000 per rupee based on comparable sale deeds from the same village, which the High Court found reasonable and supported by credible evidence. The court upheld statutory benefits including solatium and interest under applicable law. This case analysis is maintained by casestatus.in based on publicly available court records.