UNION OF INDIA THROUGH THE GENERAL MANAGER CENTRAL RAILWAY AND ORS vs LAXMAN PANDURANG PHAD — FA/389/2026
Case under Land Acquisition Act - Appeal Section 18. Disposed: --DISMISSED on 04th May 2026.
CNR: HCBM030388262023
e-Filing Number
13-09-2023
Filing Number
FA/29194/2023
Filing Date
13-Sep-2023
Registration No
FA/389/2026
Registration Date
09-Feb-2026
Judge
Hon'ble Shri Justice Shailesh P. Brahme
Coram
Hon'ble Shri Justice Shailesh P. Brahme
Bench Type
Single
Judicial Branch
Civil
Decision Date
04-May-2026
Nature of Disposal
--DISMISSED
Last updated 15-Jun-2026
Acts & Sections
Petitioner(s)
-
1.UNION OF INDIA THROUGH THE GENERAL MANAGER CENTRAL RAILWAY AND ORS
Adv. Talhar Ajay G.
-
2.THE DEPUTY CHIEF ENGINEER CONSTRUCTION CENTRAL RAILWAY
-
3.THE STATE OF MAHARASHTRA THROUGH THE COLLECTOR BEED
-
4.THE DEPUTY COLLECTOR LAND ACQUISITION JAYAKWADI PROJECT BEED TQ DIST BEED
Respondent(s)
-
1.LAXMAN PANDURANG PHAD
Case History
-
Case disposedDisposed
-
04-May-2026
Hon'ble Shri Justice Shailesh P. BrahmeView PDF
Case Summary: FA/389/2026 The High Court of Bombay at Aurangabad dismissed the Union of India's appeals challenging the Reference Court's enhancement of land acquisition compensation from Rs. 980-1180 per bigha to Rs. 4000 per bigha for agricultural land in Ghatsawali village. The court upheld the Reference Court's rate as reasonable, relying on a comparable sale deed from the same village, and found the enhancement (within four times the original award) compliant with government guidelines and statutory provisions for solatium and interest. This case analysis is maintained by casestatus.in based on publicly available court records.
-
30-Mar-2026
For Orders
Hon'ble Shri Justice Shailesh P. Brahme
-
05-Mar-2026
Hon'ble Shri Justice Shailesh P. BrahmeView PDF
-
05-Mar-2026
For Orders
Hon'ble Shri Justice Shailesh P. Brahme
-
12-Feb-2026
Hon'ble Shri Justice Shailesh P. BrahmeView PDF
-
12-Feb-2026
For Admission
Hon'ble Shri Justice Shailesh P. Brahme
-
28-Nov-2023
Objections Not Removed (First Time)
Shri Pradeep B. Ghuge (Registrar Judl.)
-
07-Nov-2023
First hearing
Initial hearing scheduled
-
13-Sep-2023
Case filed
Registration No. FA/389/2026
Case Summary: FA/389/2026 The High Court of Bombay at Aurangabad dismissed the Union of India's appeals challenging the Reference Court's enhancement of land acquisition compensation from Rs. 980-1180 per bigha to Rs. 4000 per bigha for agricultural land in Ghatsawali village. The court upheld the Reference Court's rate as reasonable, relying on a comparable sale deed from the same village, and found the enhancement (within four times the original award) compliant with government guidelines and statutory provisions for solatium and interest. This case analysis is maintained by casestatus.in based on publicly available court records.
Explore other courts