NATIONAL HIGHWAYS AUTHORITY OF INDIA, NASHIK, REPRESENTED BY IT S PROJECT DIRECTOR vs KAILASBAI BABULAL OZA AND OTHER — ARBA/10/2019

Case under Arbitration and Concilation Act 1996. Disposed: --DISMISSED on 17th April 2026.

CNR: HCBM030300202019

CASE DISPOSED

Next Hearing

23rd August 2019

Filing Number

ARBA/23010/2019

Filing Date

25-07-2019

Registration No

ARBA/10/2019

Registration Date

22-08-2019

Judge

HON'BLE SHRI JUSTICE ARUN R. PEDNEKER

Coram

HON'BLE SHRI JUSTICE ARUN R. PEDNEKER

Bench Type

Single

Category

ARBITRATION ( 4 )

Judicial Branch

Civil

Decision Date

17th April 2026

Nature of Disposal

--DISMISSED

Acts & Sections

Arbitration and Concilation Act 1996

Petitioner(s)

NATIONAL HIGHWAYS AUTHORITY OF INDIA, NASHIK, REPRESENTED BY IT S PROJECT DIRECTOR

Adv. Manorkar Deepak S

Respondent(s)

KAILASBAI BABULAL OZA AND OTHER

Adv. ADV. A. B. KALE FOR R/1 TO 9,Kale Ajeet B.,R/10 served (through Son), R/11 served (through nephew) R/12 served (through wife),Kale Ajeet B. 1123

Hearing History

Judge: HON'BLE SHRI JUSTICE ARUN R. PEDNEKER

09-10-2019

FOR ADMISSION - FRESH [CIVIL SIDE MATTERS]

27-11-2019

DUE ADMISSION [ AFTER NOTICE ]

23-08-2019

PETITIONS FOR ADMISSION - FRESH CIVIL SIDE MATTERS

24-03-2020

DUE ADMISSION -CIVIL

14-01-2020

DUE ADMISSION -CIVIL

Orders

17-04-2026
HON'BLE SHRI JUSTICE ARUN R. PEDNEKER

The High Court of Bombay at Aurangabad dismissed NHAI's arbitration appeals (Nos. 9 & 10 of 2019) against Anil D. Sonje and Kailasbai Babulal Oza, finding that NHAI's Section 34 applications under the Arbitration and Conciliation Act, 1996 were filed 26 days beyond the mandatory 3-month plus 30-day deadline, which the court has no power to condone. The court upheld the District Court's dismissal, noting strict adherence to statutory time limits. This case analysis is maintained by casestatus.in based on publicly available court records.

casestatus.in Summary

The High Court of Bombay at Aurangabad dismissed NHAI's arbitration appeals (Nos. 9 & 10 of 2019) against Anil D. Sonje and Kailasbai Babulal Oza, finding that NHAI's Section 34 applications under the Arbitration and Conciliation Act, 1996 were filed 26 days beyond the mandatory 3-month plus 30-day deadline, which the court has no power to condone. The court upheld the District Court's dismissal, noting strict adherence to statutory time limits. This case analysis is maintained by casestatus.in based on publicly available court records.